Activity-Based Supplier Costing
Levy Inc. manufactures tractors for agricultural usage. Levy purchases the engines needed for its tractors from two sources: Johnson Engines and Watson Company. The Johnson engine has a price of $1,000. The Watson engine is $900 per unit. Levy produces and sells 22,000 tractors. Of the 22,000 engines needed for the tractors, 4,000 are purchased from Johnson Engines, and 18,000 are purchased from Watson Company. The production manager, Jamie Murray, prefers the Johnson engine. However, Jan Booth, purchasing manager, maintains that the price difference is too great to buy more than the 4,000 units currently purchased. Booth also wants to maintain a significant connection with the Johnson source just in case the less expensive source cannot supply the needed quantities. Jamie, however, is convinced that the quality of the Johnson engine is worth the price difference.
Frank Wallace, the controller, has decided to use activity costing to resolve the issue. The following activity cost and supplier data have been collected:
Activity | Cost | ||
Replacing enginesa | $800,000 | ||
Expediting ordersb | 1,000,000 | ||
Repairing enginesc | 1,800,000 |
a All units are tested after assembly, and some are rejected because of engine failure. The failed engines are removed and replaced, with the supplier replacing any failed engine. The replaced engine is retested before being sold. Engine failure often causes collateral damage, and other parts often need to be replaced.
b Due to late or failed delivery of engines.
c Repair work is for units under warranty and almost invariably is due to engine failure. Repair usually means replacing the engine. This cost plus labor, transportation, and other costs make warranty work very expensive.
Watson | Johnson | |||
Engines replaced by source | 1,980 | 20 | ||
Late or failed shipments | 198 | 2 | ||
Warranty repairs (by source) | 2,440 | 60 |
Required:
1. Calculate the activity-based supplier cost per engine (acquisition cost plus supplier-related activity costs). (Round to the nearest cent.)
Watson | $ per engine |
Johnson | $ per engine |
Which of the two suppliers is the low-cost supplier?
Explain why this is a better measure of engine cost than the usual purchase costs assigned to the engines.
The engine costs less when the full supplier effects are considered. This is a better assessment of cost because it considers the costs that are caused by the supplier due to poor quality, poor reliability, and poor delivery performance.
2. Consider the supplier cost information obtained in Requirement 1. Suppose further that Johnson can only supply a total of 20,000 units. What actions would you advise Levy to undertake with its suppliers?
In the short run, buy 20,000 from and 2,000 from . In the long run, one possibility is to encourage to increase its quality and maintain purchases from both sources (lowers source risk by having two suppliers).
Answer for 1)
Cost of engines:
Particulars | Watson Engines($) | Johnson engines($) |
Price | 900 | 1000 |
Replacing engines |
44.44 ($800000/18000 engines) |
|
Expediting orders |
55.56 ($1000000/18000 engines) |
|
Repairing costs |
100 ($1800000/18000 engines) |
|
Estimated costs | 1100 | 1000 |
Note: Regardless the activity given for calculating cost, total 18000 engines will be considered as such cost incurred for every 18000 engines purchased.
The cost of Johnson Engines are low as compared to Watson engines (including all replacement,late and repair costs).
Answer for 2)
In case if Johnson company can't supply 22000 engines it is advised to purchase all the engines that it can supply i.e 20000 engines and purchase 2000 engines from Watson company. In future it is advisable to encourage Watson company to make better quality engines for getting reliable engines from both sources.