Question

Based upon the following data, what is the cost of the land? Land purchase price $192,411...

Based upon the following data, what is the cost of the land?

Land purchase price $192,411
Broker's commission 15,502
Payment for the demolition and removal of existing building 5,028
Cash received from the sale of materials salvaged from the demolished building 1,398

$

Homework Answers

Answer #1
Cost of Land
$
Land purchase price        192,411.00
Broker's commission          15,502.00
Payment for the demolition and removal of existing building            5,028.00
Cash received from the sale of materials salvaged from the demolished building          (1,398.00)
Total 211,543.00
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech...
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance $ 26,000 Legal fees for drawing the contract 5,000 Pro-rated property taxes for the period after acquisition 46,000 State transfer fees 5,000 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.2 and $1.8 million, respectively. Shortly after acquisition, Samtech spent...
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech...
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance $ 35,000 Legal fees for drawing the contract 9,500 Pro-rated property taxes for the period after acquisition 55,000 State transfer fees 5,900 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.6 and $1.2 million, respectively. Shortly after acquisition, Samtech spent...
Soccer Wholesale purchased land and a warehouse for one price of $810,000. In addition to the...
Soccer Wholesale purchased land and a warehouse for one price of $810,000. In addition to the purchase price, Soccer Wholesale makes the following expenditures related to the acquisition: broker's commission, $49,300; title insurance, $4,100; and miscellaneous closing costs, $6,300. The warehouse is immediately demolished at a cost of $78,100 in anticipation of building a new warehouse.    Determine the amount Soccer Wholesale should record as the cost of the land.
Compute the cost of land based on the following data. Purchase price of land                              &nbs
Compute the cost of land based on the following data. Purchase price of land                                                 100,000 Assumption of past due property taxes on the land        3,000 Cost of title and attorney fees                                        20,000 Cost of grading land                                                        4,000 Cost to pave parking lot                                                   8,200
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech...
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance $ 36,000 Legal fees for drawing the contract 10,000 Pro-rated property taxes for the period after acquisition 56,000 State transfer fees 6,000 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3 and $1 million, respectively. Shortly after acquisition, Samtech spent...
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech...
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title Insurance $23,000 Legal fees for drawing the contacts $8,500 Pro-rated property taxes for the period after acquisition $43,000 State transfer fees $4,700 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3 and $2 million, respectively. Shortly after acquisition, Samtech spent $89,000...
1. Assume Purchase price of the land 84133.00 Real estate commission (%) of the purchase price...
1. Assume Purchase price of the land 84133.00 Real estate commission (%) of the purchase price 6.70 Demolition of old building on site 20524.34 Sale of scrap from old building 8702.32 Construction cost of the new building 603657.00 Land survey costs 7151.30 Back taxes 9507.03 Architect fees 63383.99 The initial value of the land is: ___________ 2. During the current year, an ABC company incurred the following costs: $ R&D services performed by XYZ for ABC 97556 R&D performed by...
Use the following to answer questions 1 – 4 J&T Company purchased land as a factory...
Use the following to answer questions 1 – 4 J&T Company purchased land as a factory site.  An old building on the property was demolished, and construction began on a new building.  Costs incurred during the first year are listed below: Land purchased as a factory site $450,000 Building construction costs 1,750,000 Interest cost related to the construction 80,000 Demolition of old building 45,000 Title investigation of land 11,000 Property taxes on land (past due for last year) 5,700 Property taxes on...
On February 1, 2020, Crane Company purchased a parcel of land as a factory site for...
On February 1, 2020, Crane Company purchased a parcel of land as a factory site for $318000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2020. Costs incurred during this period are listed below: Demolition of old building $ 21000 Architect's fees 36000 Legal fees for title investigation and purchase contract 5300 Construction costs 1392000 (Salvaged materials resulting from demolition were sold for $10800.) Crane should record...
On February 1, 2020, Coronado Industries purchased a parcel of land as a factory site for...
On February 1, 2020, Coronado Industries purchased a parcel of land as a factory site for $325000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2020. Costs incurred during this period are listed below: Demolition of old building $ 21300 Architect's fees 33900 Legal fees for title investigation and purchase contract 5400 Construction costs 1379000 (Salvaged materials resulting from demolition were sold for $9600.) Coronado should record...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT