The following standards have been established for a raw material used to make product I92:         ...

The following standards have been established for a raw material used to make product I92:

        

Standard quantity of the material per unit of output................................................

6 pounds

Standard price of the material..................

$2.25 per pound

Standard hours of labor per unit of output

3 hours

Standard rate of the labor per hour

$8 per hour

The following data pertain to a recent month’s operations:

Actual material purchased......................

13,600 pounds

Actual cost of material purchased..........

$31,620

Actual material used in production........

13,600 pounds

Actual output..........................................

2,300 units of product I92

Actual labor used

7,100 hours

Actual total labor cost

$57,150

            Required:

  1. What is the materials price variance for the month?
  2. What is the materials quantity variance for the month?
  3. What is the labor rate variance for the month?
  4. What is the labor efficiency variance for the month?

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following standards have been established for a raw material used to make product O84: Standard...
The following standards have been established for a raw material used to make product O84: Standard quantity of the material per unit of output 8.9 meters Standard price of the material $ 19.00 per meter The following data pertain to a recent month's operations: Actual material purchased 5,300 meters Actual cost of material purchased $ 104,520 Actual material used in production 5,100 meters Actual output 680 units of product O84 The direct materials purchases variance is computed when the materials...
The following standards have been established for a raw material used to make product O84: Standard...
The following standards have been established for a raw material used to make product O84: Standard quantity of the material per unit of output 7.8 meters Standard price of the material $ 19.00 per meter The following data pertain to a recent month's operations: Actual material purchased 4,100 meters Actual cost of material purchased $ 81,590 Actual material used in production 3,800 meters Actual output 570 units of product O84 The direct materials purchases variance is computed when the materials...
The following standards have been established for a raw material used to make product O84: Standard...
The following standards have been established for a raw material used to make product O84: Standard quantity of the material per unit of output 7.4 meters Standard price of the material $ 18.50 per meter The following data pertain to a recent month's operations: Actual material purchased 3,700 meters Actual cost of material purchased $ 71,780 Actual material used in production 3,400 meters Actual output 530 units of product O84 The direct materials purchases variance is computed when the materials...
Domanski Incorporated has established the following raw material standards for its APL4 product: Standard quantity of...
Domanski Incorporated has established the following raw material standards for its APL4 product: Standard quantity of the material per unit of output 4.5 pounds Standard price of the material $13.90 per pound The following data pertain to a recent month's operations: Actual material purchased 2,000 pounds Actual cost of material purchased $26,200 Actual material used in production 1,300 pounds Actual output 220 units of product I92 The direct materials purchases variance is computed when the materials are purchased. Required: a....
27. The following standards for variable manufacturing overhead have been established for a company that makes...
27. The following standards for variable manufacturing overhead have been established for a company that makes only one product: Standard hours per unit of output 7.4 hours Standard variable overhead rate $ 13.80 per hour The following data pertain to operations for the last month: Actual hours 2,775 hours Actual total variable manufacturing overhead cost $ 38,995 Actual output 200 units What is the variable overhead efficiency variance for the month? Multiple Choice Top of Form $18,571 U $17,871 U...
The following labor standards have been established for a particular product: Standard labor-hours per unit of...
The following labor standards have been established for a particular product: Standard labor-hours per unit of output 2.4 hours Standard labor rate $13.95 per hour The following data pertain to operations concerning the product for the last month:    Actual hours worked 4,300 hours Actual total labor cost $50,720 Actual output 2,900 units What is the labor rate variance for the month? $9,265 F $10,847 F $3,360 F $3,360 U Jackson Industries uses a standard cost system in which direct...
The following materials standards have been established for a particular product: Standard quantity per unit of...
The following materials standards have been established for a particular product: Standard quantity per unit of output 6.0 meters Standard price $ 19.00 per meter The following data pertain to operations concerning the product for the last month: Actual materials purchased 10,200 meters Actual cost of materials purchased $ 201,500 Actual materials used in production 9,600 meters Actual output 1,580 units What is the materials price variance for the month?
The following labor standards have been established for a particular product: Standard labor hours per unit...
The following labor standards have been established for a particular product: Standard labor hours per unit of output 2.8 hours Standard labor rate $11.50 per hour The following data pertain to operations concerning the product for the last month: Actual hours worked 6,900 hours Actual total labor cost $80,385 Actual output 2,300 units Required: a. What is the labor rate variance for the month? b. What is the labor efficiency variance for the month? Solution (Please show work/calculations): a. Labor...
Al-Shabad Company produces a single product. The company has set the following standards for material and...
Al-Shabad Company produces a single product. The company has set the following standards for material and labor. Standard quantity/hours per unit standard price/rate direct materials 7 pounds per unit $7 per pound direct labor 3 hours per unit $10 per hour During the past month the company purchased 7,000 pounds of direct materials at a cost of $17,500. All of this material was used in production of 1,300 units of product. Direct labor totaled $36,750 for the month. The following...
The following labor standards have been established for a particular product: Standard labor hours per unit...
The following labor standards have been established for a particular product: Standard labor hours per unit of output 4.5 hours Standard labor rate $ 20.30 per hour The following data pertain to operations concerning the product for the last month: Actual hours worked 7,100 hours Actual total labor cost $ 144,840 Actual output 1,500 units Required: a. What is the labor rate variance for the month? b.  What is the labor efficiency variance for the month? (Indicate the effect of each...