Question

Magenta Company has identified seven activities as part of its manufacturing process and chosen corresponding activity...

Magenta Company has identified seven activities as part of its manufacturing process and chosen corresponding activity drivers for each activity. The chart below lists the total cost of each activity, the proportion of activity driver used for each of Magenta’s two products, and the activity cost assigned to each product.

Fill in the blanks below: (Round your answers to the nearest whole number.)

Proportion Used By
Activity Cost Activity Driver Prod. 1 Prod. 2 Activity Cost:Prod. 1 Activity Cost:Prod. 2
Design $40,900 Design time 57 % 43 % $23,313 $17,587
Preparation $18,100 Labor hours 56 % % $10,136
Machining $91,400 Machine hours 45 % % $41,130
Finishing $25,100 Batches 49 % % $12,299
Inspection Units % % $4,326 $5,974
Packaging Orders % 20 % $14,080
Shipping $11,300 Packages 70 % 30 % $7,910 $3,390

Homework Answers

Answer #1

Working as follows:

Please feel free to ask any query regarding the solution. Give your valuable rating. Thank You!

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
X Company uses an activity-based costing overhead allocation system. It has identified three activities - Setup,...
X Company uses an activity-based costing overhead allocation system. It has identified three activities - Setup, Product testing, Packaging - and their respective cost drivers - setup hours, tests, packages. Budgeted activity costs in 2018 were as follows: Activity Budgeted Cost Setup $108,000 Product testing 58,600 Packaging 58,700 The following 2018 cost driver information is available for one of its products, Product X, and for all of its products (including Product X): Product X All Products setup hours 29,700 771,429...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Total Cost of Pool Cost Driver Estimated Cost Driver Machining $ 380,120 Number of machine hours 88,400 Designing costs 86,400 Number of design hours 9,000 Setup costs 74,672 Number of batches 525 Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Product A Product B Product C Number of machine hours 34,000...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Total Cost of Pool Cost Driver Estimated Cost Driver Machining $ 380,120 Number of machine hours 88,400 Designing costs 86,400 Number of design hours 9,000 Setup costs 74,672 Number of batches 525 Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Product A Product B Product C Number of machine hours 34,000...
Swifty Company identifies three activities in its manufacturing process: machine setups, machining, and inspections. Estimated annual...
Swifty Company identifies three activities in its manufacturing process: machine setups, machining, and inspections. Estimated annual overhead cost for each activity is $205,900, $411,200, and $58,500, respectively. The cost driver for each activity and the estimated annual usage are number of setups 2,900, machine hours 25,700, and number of inspections 1,300. Compute the overhead rate for each activity. Machine setups $enter a dollar amount per setup per setup Machining $enter a dollar amount per machine hour per machine hour Inspections...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000 setup hours) $118,000 Production scheduling (400 batches) 60,000 Production engineering (60 change orders) 150,000 Supervision (2,000 direct labor hours) 46,000 Machine maintenance (12,000 machine hours) 60,000 Total activity costs $434,000 The following additional data were provided for Job 845: Direct materials costs $7,000 Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) $1,000 Setup hours 5...