Question

Which of the following statements is true about the internal rate of return (IRR)? a.If the...

Which of the following statements is true about the internal rate of return (IRR)?

a.If the IRR is less than the required rate of return, the firm is indifferent between accepting or rejecting the investment proposal.

b.If the IRR is greater than the required rate, the project is deemed acceptable.

c.If the IRR is less than the required rate of return, the project is deemed acceptable.

d.If the IRR is greater than the required rate of return, the firm is indifferent between accepting or rejecting the investment proposal.

Homework Answers

Answer #1

The correct answer is

B) If the IRR is greater than the required rate, the project is deemed acceptable

explanation

Internal rate of return refers to the rate at which the present value of inflows and outflows are same and NPV is Zero. Higher the IRR it is more better the project is. If the IRR is greater then the required rate of return then the project is acceptable because then at required rate of return NPV will be positive as this rate is less then IRR.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the following statements about internal rate of return (IRR) is false? explain why IRR...
Which of the following statements about internal rate of return (IRR) is false? explain why IRR is the discount rate at which the present value of future expected cash flows is exactly equal to the initial investment. The IRR rule always leads to the same decision as the NPV rule. IRR is the discount rate at which a project's NPV equals zero.
Which one of the following statements is TRUE? Group of answer choices When the required return...
Which one of the following statements is TRUE? Group of answer choices When the required return is less than the internal rate of return, net present value is positive. When the IRR is greater than the required return, the net present value is negative. If projects are mutually exclusive, you should always select the project with the greatest IRR. Projects with conventional cash flows have multiple internal rates of return.
4. Internal rate of return (IRR) The internal rate of return (IRR) refers to the compound...
4. Internal rate of return (IRR) The internal rate of return (IRR) refers to the compound annual rate of return that a project generates based on its up-front cost and subsequent cash flows. Consider the case of Blue Llama Mining Company: Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Sigma) that will require an initial investment of $800,000. The company has been basing capital budgeting decisions on a project’s NPV; however, its new CFO wants to...
Internal rate of return   For the project shown in the following​ table, calculate the internal rate...
Internal rate of return   For the project shown in the following​ table, calculate the internal rate of return ​(IRR). Then​ indicate, for the​ project, the maximum cost of capital that the firm could have and still find the IRR acceptable. Initial investment   $160,000 Year (t)   Cash inflows 1   $35,000 2   $25,000 3   $45,000 4   $45,000 5   $45,000 The​ project's IRR is? The maximum cost of capital that the firm could have and still find the IRR acceptable is?
Which of the following statements defines the internal rate of return (IRR) for a project? A....
Which of the following statements defines the internal rate of return (IRR) for a project? A. Discount rate which results in a zero NPV B. Discount rate which results in a NPV equal to the project's initial cost C. Rate of return required by the project's investors D. The current market rate of return for projects of similar risk
For the project shown in the following​ table, calculate the internal rate of return ​(IRR). Then​...
For the project shown in the following​ table, calculate the internal rate of return ​(IRR). Then​ indicate, for the​ project, the maximum cost of capital that the firm could have and still find the IRR acceptable. Initial investment ​(CF 0CF0​) ​$80,000 Year ​(t​) Cash inflows ​(CF Subscript tCFt​) 1 ​$25,000 2 ​$45,000 3 ​$30,000 4 ​$30,000 5 ​$15,000
Which of the following is statements related to capital budgeting is not true? A project is...
Which of the following is statements related to capital budgeting is not true? A project is considered acceptable if its NPV is greater zero. A project whose NPV is greater than its IRR is should be accepted. Both the NPV method and the IRR method of evaluating capital investment projects are widely considered to be superior to the payback method. An NPV of zero signifies that the project's cash flows are just sufficient to repay the invested capital and to...
8. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
8. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation : Cute Camel Woodcraft Company is analyzing a project that requires an initial investment of $3,225,000....
Which of the following statements is​ true? A.If interest rates remain​ constant, the value of premium...
Which of the following statements is​ true? A.If interest rates remain​ constant, the value of premium bonds will increase over time. B.If interest rates​ increase, the value of a bond will increase. C.The value of a bond is inversely related to changes in​ investors' present required rate of return. D.interest rates​ decrease, the value of a bond will decrease.
Internal rate of return For the project shown in the following​ table, calculate the internal rate...
Internal rate of return For the project shown in the following​ table, calculate the internal rate of return ​(IRR). Then​ indicate, for the​ project, the maximum cost of capital that the firm could have and still find the IRR acceptable. The​ project's IRR is ​%. (Round to two decimal​ places.) Initial investment ​(CF 0CF0​) $110,000 Year ​(t​) Cash inflows ​(CF Subscript tCFt​) 1 $25,000 2 $50,000 3 $30,000 4 $35,000 5 $10,000
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT