Uninder Company uses the high-low method to estimate the cost function. The information for 2015 is provided below:
Machine-hours Labor Costs
Highest observation of cost driver 550 $22,000
Lowest observation of cost driver 250 $ 13,000
What is the estimated total cost when 400 machine-hours are used?
a. $17,500
b. $29,000
c. $16,000
d. $20,800
a. $17,500 | ||
Machine-hours | Labor Costs | |
Highest | 550 | $22,000 |
Lowest | 250 | $13,000 |
Differnce | 300 | $9,000 |
Variable cost of sales = | $30.00 | |
($9,000/300) | ||
Fixed cost | $5,500 | |
$22,000 - (550 x $30) | ||
Total cost when 400 machine-hours are used | $17,500 | |
(400 x $30) + $5,500 | ||