Question

The difference between the actual variable factory overhead costs and the budgeted variable overhead for actual...

The difference between the actual variable factory overhead costs and the budgeted variable overhead for actual production is termed variable factory overhead controllable variance. True False

Homework Answers

Answer #1

False,

actual variable factory overhead costs= Actual Labour hrs * Actual variable overhead rate per hour

budgeted variable overhead for actual production=Actual Labour hrs * Std variable overhead rate per hour

Variance=Actual Labour hrs*( Actual variable overhead rate per hour-Std variable overhead rate per hour)

from above formula we can understand that variable overhead rate is changes so, variable over rate (fixed per unit) which is not in the control of entity so, it is not controllable variance

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Variable Factory Overhead Controllable Variance = Actual Variable Factory Overhead – Budgeted Variable Factory Overhead Group...
Variable Factory Overhead Controllable Variance = Actual Variable Factory Overhead – Budgeted Variable Factory Overhead Group of answer choices A) True B) False
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead...
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead along with the related controllable and volume variances.Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. A detailed estimate of what a product should cost.Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 6,800 units of product were as follows: Standard Costs Actual Costs Direct materials 8,800 lb. at $4.90 8,700...
The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable...
The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable factory overhead $223,100 Fixed factory overhead 94,250 Standard: 8,000 hrs. at $36 288,000 If productive capacity of 100% was 13,000 hours and the total factory overhead cost budgeted at the level of 8,000 standard hours was $324,250, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was $7.25 per hour....
The following data relate to factory overhead cost for the production of 15,000 computers: Actual: Variable...
The following data relate to factory overhead cost for the production of 15,000 computers: Actual: Variable factory overhead $240,000 Fixed factory overhead 160,000 Standard: 19,500 hrs. at $20 390,000 If productive capacity of 100% was 20,000 hours and the total factory overhead cost budgeted at the level of 19,500 standard hours was $394,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was $8.00 per hour....
The following data relate to factory overhead cost for the production of 5,000 computers: Actual: Variable...
The following data relate to factory overhead cost for the production of 5,000 computers: Actual: Variable factory overhead $141,900 Fixed factory overhead 46,000 Standard: 5,000 hrs. at $35 175,000 If productive capacity of 100% was 8,000 hours and the total factory overhead cost budgeted at the level of 5,000 standard hours was $192,250, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and totalfactory overhead cost variance. The fixed factory overhead rate was $5.75 per hour. Enter...
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.78 per hour Variable overhead 3 hours per unit @ $1.91 per hour Actual Costs     Total variable cost, $17,800     Total fixed cost, $8,100 The variable factory overhead controllable variance is a.$1,756 favorable b.$1,756 unfavorable c.$1,405 favorable d.$0
1. Standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...
1. Standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.77 per hour Variable overhead 3 hours per unit @ $1.91 per hour Actual Costs     Total variable cost, $18,100     Total fixed cost, $8,200 The amount of the variable factory overhead controllable variance is a.$2,056 favorable b.$0 c.$2,056 unfavorable d.$1,645 favorable
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of...
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.72 per hour Variable overhead 3 hours per unit @ $2.06 per hour Actual Costs     Total variable cost, $18,000     Total fixed cost, $7,900 The fixed factory overhead volume variance is a.$720 unfavorable b.$0 c.$576 unfavorable d.$576 favorable The following data are given for Bahia Company: Budgeted...
The difference between budgeted fixed manufacturing overhead and the fixed overhead applied to production is the:...
The difference between budgeted fixed manufacturing overhead and the fixed overhead applied to production is the: Select one: a. sum of the spending and efficiency variances. b. efficiency variance. c. spending variance. d. volume variance. e. controllable variance.
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable factory overhead $190,100 Fixed factory overhead 45,500 Standard: 8,000 hrs. at $28 224,000 If productive capacity of 100% was 13,000 hours and the factory overhead cost budgeted at the level of 8,000 standard hours was $241,500, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT