Question

Question 4: Eric Co. uses machine hours to apply standard overhead cost to production. The following...

Question 4:

Eric Co. uses machine hours to apply standard overhead cost to production. The following data pertain to October:

Master budget data:

Units

2,500

Total machine hours (denominator volume)

100,000

Total variable overhead cost

$

250,000

Total fixed overhead cost

$

50,000

Actual operating results:

Variable overhead cost incurred

$

265,000

Fixed overhead cost incurred

$

54,000

Units manufactured

2,250

Total machine hours

96,000

Required: Compute the following variances using machine hours as the activity variable used to assign standard overhead costs to production. Show calculations, indicate favorable / unfavorable, and provide a short description (i.e., interpretation) of each of the variances.

1. Variable overhead spending variance

2. Variable overhead efficiency variance

3. Fixed overhead spending variance

4. Fixed overhead production-volume variance.

Please explain and show work. Will rate.

Homework Answers

Answer #1

Solution 1 & 2:

Standard machine hours per unit = 100,000/2500 = 40 hours

Standard rate of variable overhead = $250,000 / 100000 = $2.50 per machine hour

Standard hours of actual production = 2250*40 = 90000 hours

Actual rate of variable overhead = $265,000 /96000 = $2.76041666

Variable overhead spending variance = (SR - AR) * AH = ($2.50 - $2.76041666) * 96000 = $25,000 U

Variable overhead efficiency variance = (SH - AH) * SR = (90000- 96000) * $2.50 = $15,000 U

Solution 3&4:

Budgeted fixed overhead = $50,000

Actual fixed overhead = $54,000

Fixed overhead rate = $50,000 / 100000 = $0.50 per machine hour

Fixed overhead applied = 90000 * $0.50 = $45,000

Fixed overhead spending variance = Budgeted fixed overhead - Actual fixed overhead = $50,000 - $54,000 = $4,000 U

Fixed overhead volume variance = Fixed overhead applied - Budgeted fixed overhead = $45,000 - $50,000 = $5,000 U

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Alden Company uses a two-variance analysis for overhead variances. Practical capacity is defined as 36 setups...
Alden Company uses a two-variance analysis for overhead variances. Practical capacity is defined as 36 setups and 36,000 machine hours to manufacture 7,200 units for the year. Selected data for 2016 follow:   Budgeted fixed factory overhead:      Setup   $ 57,600         Other 265,000 $ 322,600   Total factory overhead incurred $ 494,000   Variable factory overhead rate:      Per setup $ 650      Per machine hour $ 4   Total standard machine hours allowed for the units manufactured 24,000 hours   Machine hours actually worked 28,000 hours...
Answer questions 18-21 using the information below: Thinnews Co., uses machine hours to allocate manufacturing overhead...
Answer questions 18-21 using the information below: Thinnews Co., uses machine hours to allocate manufacturing overhead cost to outputs: Actual total overhead cost incurred $ 24,000 Actual fixed overhead cost incurred $ 10,000 Budgeted fixed overhead cost $ 11,000 Actual machine hours 5,000 Standard machine hours allowed for the units manufactured 4,800 Denominator level — machine hours 5,500 Standard variable overhead rate per machine hour $ 3.00 What is variable overhead spending variance? Group of answer choices $960 favorable $1,000...
Maxima Corp. uses a standard cost system with machine-hours as the activity base for both variable...
Maxima Corp. uses a standard cost system with machine-hours as the activity base for both variable and fixed manufacturing overhead (VMOH & FMOH). The following information relates to production for last year: Variable Fixed Total budgeted overhead (at the denominator level of activity) $14,000 ? Total applied overhead $15,400 $28,600 Total actual overhead $15,700 $31,800 The actual machine-hours incurred were 2,300. VMOH Efficiency Variance was $700 Unfavorable. What was Maxima's FMOH Volume Variance?
Maxima Corp. uses a standard cost system with machine-hours as the activity base for both variable...
Maxima Corp. uses a standard cost system with machine-hours as the activity base for both variable and fixed manufacturing overhead (VMOH & FMOH). The following information relates to production for last year: Variable Fixed Total budgeted overhead (at the denominator level of activity) $14,000 ? Total applied overhead $15,400 $28,600 Total actual overhead $15,700 $31,800 The actual machine-hours incurred were 2,300. VMOH Efficiency Variance was $700 Unfavorable. What was Maxima's FMOH Volume Variance?
Alden Company uses a two-variance analysis for overhead variances. Practical capacity is defined as 36 setups...
Alden Company uses a two-variance analysis for overhead variances. Practical capacity is defined as 36 setups and 36,000 machine hours to manufacture 7,200 units for the year. Selected data for 2016 follow:   Budgeted fixed factory overhead:      Setup   $ 57,600         Other 265,000 $ 322,600   Total factory overhead incurred $ 494,000   Variable factory overhead rate:      Per setup $ 650      Per machine hour $ 4   Total standard machine hours allowed for the units manufactured 24,000 hours   Machine hours actually worked 28,000 hours...
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced....
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,800 machine hours per year, which represents 27,900 units of output. Annual budgeted fixed overhead costs are $279,000 and the budgeted variable overhead cost rate is $3.90 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 21,700 units, which...
Maxwell Company uses a standard cost accounting system and applies production overhead to products on the...
Maxwell Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the year just ended: Standard variable-overhead rate per hour: $7.50 Standard fixed-overhead rate per hour: $12.40 Planned activity during the period: 19,000 machine hours Actual production: 12,200 finished units Machine-hour standard: Two completed units per machine hour Actual variable overhead: $153,180 Actual total overhead: $432,900 Actual machine hours worked: 22,200 Required: 1. Calculate the...
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced....
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,500 machine hours per year, which represents 27,750 units of output. Annual budgeted fixed overhead costs are $277,500 and the budgeted variable overhead cost rate is $3.80 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 21,600 units, which...
The following information for the past year is available from Thinnews Co., a company that uses...
The following information for the past year is available from Thinnews Co., a company that uses machine hours to apply standard factory overhead cost to outputs: Actual total factory overhead cost incurred $ 30,000 Actual fixed overhead cost incurred $ 7,000 Budgeted fixed overhead cost $ 12,000 Actual machine hours 8,000 Standard machine hours allowed for the units manufactured 4,600 Denominator volume—machine hours 7,500 Standard variable overhead rate per machine hour $ 3 The variable overhead spending variance, to the...
The following information for the past year is available from Thinnews Co., a company that uses...
The following information for the past year is available from Thinnews Co., a company that uses machine hours to apply standard factory overhead cost to outputs: Actual total factory overhead cost incurred $ 24,000 Actual fixed overhead cost incurred $ 10,000 Budgeted fixed overhead cost $ 11,000 Actual machine hours 5,000 Standard machine hours allowed for the units manufactured 4,800 Denominator volume—machine hours 5,500 Standard variable overhead rate per machine hour $ 3.00 Under a three-variance breakdown (decomposition) of the...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT