Marquis Company estimates that annual manufacturing overhead
costs will be $822,600. Estimated annual operating activity bases
are direct labor cost $457,000, direct labor hours 45,700, and
machine hours 91,400.
Compute the predetermined overhead rate for each activity base.
(Round answers to 2 decimal places, e.g. 10.50% or
10.50.)
Overhead rate per direct labor cost | |||
---|---|---|---|
Overhead rate per direct labor hour | |||
Overhead rate per machine hour |
Answer:
Computation of the predetermined overhead rate for each activity base:
Overhead rate per direct labor cost | 180.00% |
Overhead rate per direct labor hour | $18.00 |
Overhead rate per machine hour | $9.00 |
Based on direct labour cost:
Overhead rate per direct labor cost = (Budeted overhead costs / Budgeted direct labor cost) x 100
= ($822,600 / $457,000) x 100
= 180.00%
Based on direct labor hours:
Overhead rate per direct labor hours = Budgeted overhead costs / budgeted direct labor hours
= $822,600 / 45,700
= $18.00 per direct labor hour
Based on machine hours:
Overhead rate per machine hours = Budgeted overhead costs / Budeted machine hours
= $822,600 / 91,400
= $9.00 per machine hour