Question

Use a weighted score model to choose between three different financing methods (A,B,C) for a project....

Use a weighted score model to choose between three different financing methods (A,B,C) for a project. The relative weights for each criterion are shown in the following table, as are the scores for each, the higher the value, the more favourable the score.

Project Characteristics Weigh A B C
Consulting Cost 20 1 2 3
Acquisition period 10 2 3 1
Disruption 10 2 1 3
Project risk 10 3 3 2
Required infrastructure 20 1 2 2
required equipment 10 2 2 2
Duration 20 1 2 2

Which is the best approach (A,B,C)

A) A

B) B

C) C

D) B and C are equivalent

Homework Answers

Answer #1

Correct Answer:

The best Approach is C, as the weighted score is the highest among A, B, C.

Working:

Project Characteristics

Weigh

A

B

C

A

B

C

Consulting cost

20

1

2

3

20

40

60

acquisition cost

10

2

3

1

20

30

10

Disruption

10

2

1

3

20

10

30

Project Risk

10

3

3

2

30

30

20

Required infrastructure

20

1

2

2

20

40

40

Required equipment

10

2

2

2

20

20

20

Duration

20

1

2

2

20

40

40

Total Score

150

210

220

End of answer.

Thanks.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Use C++ to design a program: Your program will use three different 5-point numerical quadrature methods...
Use C++ to design a program: Your program will use three different 5-point numerical quadrature methods (Closed Newton Cotes, Gaussian Quadrature, and Lobatto Quadrature) You will employ each of these methods to solve each of the following three problems to find the area under the respective curves over the interval (-1, 1). The following is a plot of the first function f(x) = 1 - sin(1 - x)    The true area under the curve is (to 20 digits) 0.58385316345285761300.              ...
Beagle Clothiers uses a weighted score for the evaluation and selection of its suppliers of trendy...
Beagle Clothiers uses a weighted score for the evaluation and selection of its suppliers of trendy fashion garments. Each supplier is rated on a​ 10-point scale ​(10=​highest) for four different​ criteria: price,​ quality, delivery, and flexibility​ (to accommodate changes in quantity and​ timing). Because of the volatility of the business in which Beagle​ operates, flexibility is given twice the weight of each of the other three​ criteria, which are equally weighted​ (the sum of the four weights equals​ 1). The...
Year:           Project A      Project B         Project C     Product D       Project E
Year:           Project A      Project B         Project C     Product D       Project E 0                   (10,000) (15,000)         (20,000)       (50,000)          (100,000) 1                      4,000          8,000 7,000          10,000              33,000 2                      4,000 6,000 7,000          15,000              40,000 3                      4,000          4,000 7,000          (5,000)              33,000 4                       ------           2,000    7,000 20,000              40,000 5                       ------   -----    ------           10,000              (10,000) 6                       ------             ------ ------           (1,000) ------ 1. Calculate the payback of each project. 2. Calculate the discounted payback of each project (assume a cost-of-capital of 10 percent). 3. Calculate the NPV of each project (again, assume 10 percent). 4. Calculate the PI of each project (again, assume...
A project has three activities A, B, and C that must be carried out sequentially. -----...
A project has three activities A, B, and C that must be carried out sequentially. ----- A -----> ----B----> ------C------> The probability distributions of the times required to complete each of the activities A, B, and C are uniformly distributed in intervals (1,5], (2,8] and (3,6] days respectively. The project completion time is the sum of times to finish all three activities. Run 1000 simulation trials in Excel to simulate the project. Which of the following Excel functions would generate...
The company has to choose between to mutually exclusive projects, Project A and Project B. Which...
The company has to choose between to mutually exclusive projects, Project A and Project B. Which project (s) should the company implement if they have a 10% required rate of return? Year Project A Project B 0 $-50,000 $-10,000 1 $20,000 $5,000 2 $20,000 $5,000 3 $10,000 $2,000 4 $10,000 $2,000 5 $5000 $1500 Question 8 options: Only A Only B A & B Neither A nor B
I cannot find the Weighted-average lower-of-cost-or-market. Lower-of-Cost-or-Market For the weighted-average method, round calculations to two decimal...
I cannot find the Weighted-average lower-of-cost-or-market. Lower-of-Cost-or-Market For the weighted-average method, round calculations to two decimal places. If required, round your final answers to the nearest cent. 1. Calculate the total amount to be assigned to the ending inventory under each of the following periodic inventory methods: a. FIFO b. Weighted-average 2. Assume that the market price per unit (cost to replace) of Stalberg's inventory on December 31, 20--, was $26. Calculate the total amount to be assigned to the...
Globex Corp. has to choose between two mutually exclusive projects. If it chooses project A, Globex...
Globex Corp. has to choose between two mutually exclusive projects. If it chooses project A, Globex Corp. will have the opportunity to make a similar investment in three years. However, if it chooses project B, it will not have the opportunity to make a second investment. The following table lists the cash flows for these projects. If the firm uses the replacement chain (common life) approach, what will be the difference between the net present value (NPV) of project A...
You are considering three independent projects, Project A, Project B and Project C. Given the following...
You are considering three independent projects, Project A, Project B and Project C. Given the following cash flow information, calculate the payback period for each. Year Project A Project B Project C 0 (Investment) ($ 900) ($ 9,000) ( $7,000) 1 $ 600 $ 5,000 $ 2,000 2 $ 300 $ 3,000 $ 2,000 3 $ 200 $ 3,000 $ 2,000 4 $ 100 $ 3,000 $ 2,000 5 $ 500 $ 3,000 $ 2,000
For the weighted-average method, round calculations to two decimal places. If required, round your final answers...
For the weighted-average method, round calculations to two decimal places. If required, round your final answers to the nearest cent. Instructions: For the weighted-average method, round calculations to two decimal places. If required, round your final answers to the nearest cent. 1. Calculate the total amount to be assigned to the ending inventory under each of the following periodic inventory methods. 2. Assume that the market price per unit (cost to replace) of Stalberg's inventory on December 31, 20--, was...
An industrial engineer is investigating the effect of four assembly methods (A, B, C, and D)...
An industrial engineer is investigating the effect of four assembly methods (A, B, C, and D) on the assembly time for a color television component. Four operators are selected for the study. Furthermore, the engineer knows that each assembly method produces such fatigue that the time required for the last assembly may be greater than the time required for the first, regardless of the method. To account for this source of variability, the engineer uses the design below. explain the...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT