Following information is available in respect of a particular material used by CTLS Limited.
• Minimum materials consumption - 80 units per day
• Maximum materials consumption - 120 units per day
• Re-order quantity - 4 800 units
• Re-order period - Minimum 20 days Maximum 30 days
Using the above information, calculate;
i. Re-order level
ii. Maximum stock level
iii. Minimum stock level
iv. Average stock level
Re-order level = Reorder level is quantity where we should place the order so we can't be out of stock till the delivery is received.
(i)Reorder level = Maximum consumption × Maximum Re-order period
120 unit × 30 days = 3600 units
(ii) Maximum stock level = Reorder Level + Reorder quantity -(minimum consumption× Minimum reorder period)
= 3600units+4800units - (80 units × 20 days )
= 6800 units
(iii) Minimum stock level = Re ordering level -(normal consumption × Normal reorder period )
Minimum stock level = 3600units - ( 100 units × 25 days)
= 1100 units
(iv) Average stock level = Minimum stock level + (Re order quantity/2)
Average stock level = 1100 units + (4800units/2)
= 3500 units