Question

For the NPV of a 3-year project, are the following included in incremental cash flows and...

For the NPV of a 3-year project, are the following included in incremental cash flows and if so where?:

(a) a 3-year lease agreement, paid before the project starts

(b) a bank loan needed to pay for half of the equipment for the project.

(c) interest payments of the above bank loan

Homework Answers

Answer #1

(a) A 3-year lease agreement, paid before the project starts- Not included in incremental cash flows. It is paid before project starts and hence sunk cost and not relevant for evaluation of project

(b) a bank loan needed to pay for half of the equipment for the project.- not part of incremental cash flows since it is financing activity and not relating to operating activity to calculate incremental cash flow

(c) Interest payments of the above bank loan – Interest element is not part of incremental cash flow evaluation

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Calculate the NPV of the following project cash flows which come in at the end of...
Calculate the NPV of the following project cash flows which come in at the end of the year: $500 in Year 1, $700 in Year 2, and $1000 in Year 3; using a discount rate of 7%. The firm has a net expense of $1700 at the beginning of the project.
Manheim Candles is considering a project with the following incremental cash flows. Assume a discount rate...
Manheim Candles is considering a project with the following incremental cash flows. Assume a discount rate of 10%.             Year                           Cash Flow ($15,000) $10,000 $20,000 $30,000             Calculate the discounted payback period of the project.
Given the following cash flows for a capital project, calculate the NPV and IRR. The required...
Given the following cash flows for a capital project, calculate the NPV and IRR. The required rate of return is 8 percent. Year 0 1 2 3 4 5 Cash Flows $-37004 $11550 $12750 $16800 $10700 $5350 NPV=4947. IRR=18.0% NPV=4947. IRR=9.9% NPV=9464. IRR=9.9% NPV=9464. IRR=18.0%
A project has the following cash flows: year 0 = -500 year 1 = $140.00 year...
A project has the following cash flows: year 0 = -500 year 1 = $140.00 year 2 = $200.00 year 3 = $310.00 What is the project's NPV if the interest rate is 6%?
A project has the following projected cash flows Year 0- R280,000( investment) Year 1 R70,000 Year...
A project has the following projected cash flows Year 0- R280,000( investment) Year 1 R70,000 Year 2 R100,000 Year 3 R130,000 a) Assuming a discount rate of 10% what is the Net Present Value (NPV) of this project over the 3 year period? b) Based on your answer above, should the project be recommended for acceptance? c) would your answer to b above change if the discount rate was 5%? Why? d) what do you understand by the term nominal...
1.      Using the incremental cash flows, and WACC computes the following and the state in each...
1.      Using the incremental cash flows, and WACC computes the following and the state in each case whether the company should go ahead with the project. WACC is 10.76% Net Cash Flow 0 years 2015 1 year 2016 2 years 2017 3 year 2018 4 year 2019 ($26,000) $6,582 $7,194 $6,948 $ 23,999          a.      Payback          b.      NPV c.      IRR          d.      Profitability Index
. Calculate the IRR and NPV for the following cash flows. Assume a 15% discount rate...
. Calculate the IRR and NPV for the following cash flows. Assume a 15% discount rate Year Project 1 Cash flow Project 2 Cash flow 0 -$20,000 -$20,000 1 1,000 12,000 2 3,000 15,000 3 4,000 3,000 4 12,000 4,000 5 15,000 1,000 9. If your tenant pays you rent of $24,000 a year for 10 years, what is the present value of the series of payments discounted at 10% annually? 10. You are going to invest $300,000 in a...
Answer Question 1-3 Project A has the following projected cash flows: Year           Cash Flow 0                -11,23
Answer Question 1-3 Project A has the following projected cash flows: Year           Cash Flow 0                -11,235 1                4,400 2                4,400 3                4,400 4                4,400 5                7,400 Q1) The NPV of the above project is $_____. Assume a discount rate of 6%. a)9541 b)20776 c)17623 d)6388 Q2) The IRR for the above project is __ %. a)21.09 b)26.76 c)33.95 d)31.25 Q3)Which of the following statement is correct? a)If the discount rate increases, the IRR will decrease. b)If the discount rate increases, the NPV will stay the same. c)If...
1. Calculating project cash flows: Why do we use forecasted incremental after-tax free cash flows instead...
1. Calculating project cash flows: Why do we use forecasted incremental after-tax free cash flows instead of forecasted accounting earnings in estimating the NPV of a project? 2. The FCF calculation: How do we calculate incremental after-tax free cash flows from forecasted earnings of a project? What are the common adjustment items? 3. The FCF calculation: How do we adjust for depreciation when we calculate incremental after-tax free cash flow from EBITDA? What is the intuition for the adjustment? 4....
Calculate the NPV for a project with the following cash flows. The discount rate (weighted average...
Calculate the NPV for a project with the following cash flows. The discount rate (weighted average cost of capital) is 7% and the initial investment is $50,000.    Cash flow each year: Year 1: $10,000 Year 2:  $12,000     Year 3: $15,000 Year 4: $15,000   Year 5: $15,000    Answer: ___________________________ (12 pts)
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT