Question

Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers....

Applying Overhead to Jobs, Costing Jobs

Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,700 and Job 94 with a beginning balance of $7,200. Jagjit applies overhead at the rate of $6 per direct labor hour. Direct labor wages average $18 per hour. Data on August costs for all jobs are as follows:

Job 93 Job 94 Job 95 Job 96
Direct materials $930 $4,530 $3,230 $1,310
Direct labor cost 2,520 5,940 2,340 900

During August, Jobs 95 and 96 were started. Job 93 was completed on August 17, and the client was billed at cost plus 40%. All other jobs remained in process.

Required:

1. Calculate the number of direct labor hours that were worked on each job in August.

Job 93 DLH
Job 94 DLH
Job 95 DLH
Job 96 DLH

2. Calculate the overhead applied to each job during the month of August.

Job 93 $
Job 94 $
Job 95 $
Job 96 $

3. Prepare job-order cost sheets for each job as of the end of August. All amount cells must have an entry; enter zeros as needed.

Jagjit Company
Job-Order Cost Sheets
August 31
Job 93 Job 94 Job 95 Job 96
Beginning balance $ $ $ $
Direct materials
Direct labor
Applied overhead
Total $ $ $ $

4. Calculate the balance in Work in Process on August 31.
The work in process balance on August 31 is $.

5. What is the price of Job 93?
The price of Job 93 is $.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two...
Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,650, and Job 94 with a beginning balance of $7,270. Jagjit applies overhead at the rate of $9 per direct labor hour. Direct labor wages average $16 per hour. Data on August costs for all jobs are as follows: Job 93 Job 94 Job 95 Job 96 Direct materials $910 $4,590 $3,330 $1,270 Direct...
Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On...
Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18,710 to date. During October, Jobs 878, 879, and 880 were started. Data on costs added during October for all jobs are as follows: Job 877 Job 878 Job 879 Job 880 Direct materials $14,380 $5,960 $3,550 $1,790 Direct labor 14,600 8,200 1,700 1,900 Overhead is applied to production at the rate of...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Sheds, Inc. designs and builds sheds and outbuildings for individual customers. The company uses a job...
Sheds, Inc. designs and builds sheds and outbuildings for individual customers. The company uses a job cost system and treats each customer's order as a separate job. At the beginning of January the company had the following raw material inventory: $600 At the beginning of January the company had the following work-in-process inventories: Job 21 $13,000 Job 25 $9,000 During January, the following activities took place: 1. Started jobs 26 and 27. 2. Purchased raw materials in January: $12,000 Requisitioned...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of March, Mendez Company had two jobs in process, Job 86 and Job 87, with the following accumulated cost information: Job 86 Job 87 Direct materials $4,800 $1,600 Direct labor 1,200 3,000 Applied overhead 888 2,220 Balance, March 1 $6,888 $6,820 During March, two more jobs (88 and 89) were started. The following direct materials and direct labor costs were added to...
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $13.00 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 64,200 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials ? Direct labor ? Manufacturing overhead applied ? Total job cost $ 1,620,000 Job Omega Direct...
Snappy Company uses job-order costing and applies overhead costs to jobs using a pre-determined overhead rate...
Snappy Company uses job-order costing and applies overhead costs to jobs using a pre-determined overhead rate of $12 per direct labor hour. During 2020, Snappy Company worked on the following jobs Job #16 Job #28 Job #35 beginning cost ............. $3,500 $1,600 $2,000 direct materials used ...... $2,800 $3,700 $2,600 direct labor cost .......... $2,000 $5,300 $3,600 direct labor hours ......... 200 hours 300 hours 280 hours By the end of 2020, Job #16 and Job #28 had been completed....
ABC Manufacturing uses normal costing and allocates manufacturing overhead to jobs based on a budgeted direct...
ABC Manufacturing uses normal costing and allocates manufacturing overhead to jobs based on a budgeted direct labor-hour rate for the actual direct labor hours. Any overallocated or underallocated overhead is written-off to the cost of goods sold at the end of the month. During April 2019, ABC Manufacturing recorded the following: Budgeted manufacturing overhead costs: $400,000 Budgeted direct labor-hours: 20,000 DLHRS Budgeted machine hours: 16,000 MHRS Actual manufacturing overhead costs: $360,000 Actual direct labor-hours:   22,500 DLHRS Actual machine hours: 15,000...
Determine cost of jobs and ending balance in work in process and overhead accounts. (LO 2,...
Determine cost of jobs and ending balance in work in process and overhead accounts. (LO 2, 3, 4), AP Don Lieberman and Associates, a CPA firm, uses job order costing to capture the costs of its audit jobs. There were no audit jobs in process at the beginning of November. Listed below are data concerning the three audit jobs conducted during November. Lynn Brian Mike Direct materials $600 $400 $200 Auditor labor costs $5,400 $6,600 $3,375 Auditor hours 72 88...