THE FOLOWING INFORMATION IS USED FOR QUESTIONS 11 – 13. |
||||||||||||||||||||||||||||||||
Test Company uses an activity-based cost system and has identified the following overhead activities, estimated costs, cost drivers, and estimated usage for the coming period.
Test Company expects to use 10,500 direct labor hours for the period. The accounting records showed the following actual results for the production of A Product during the period
|
Calculate the activity rate for the machining activity.
$20 per direct labor hour |
||
$10.50 per machine hour |
||
$0.50 per direct labor hour |
||
$42 per machine hour |
QUESTION 12
THE FOLOWING INFORMATION IS USED FOR QUESTIONS 11 – 13. |
||||||||||||||||||||||||||||||||
Test Company uses an activity-based cost system and has identified the following overhead activities, estimated costs, cost drivers, and estimated usage for the coming period.
Test Company expects to use 10,500 direct labor hours for the period. The accounting records showed the following actual results for the production of A Product during the period
|
Calculate the machining cost assigned to A Product.
$210,000 |
||
$52,500 |
||
$60,000 |
||
$1,500 |
QUESTION 13
THE FOLOWING INFORMATION IS USED FOR QUESTIONS 11 – 13. |
||||||||||||||||||||||||||||||||
Test Company uses an activity-based cost system and has identified the following overhead activities, estimated costs, cost drivers, and estimated usage for the coming period.
Test Company expects to use 10,500 direct labor hours for the period. The accounting records showed the following actual results for the production of A Product during the period
|
Calculate the total product cost for A Product.
$96,500 |
||
$390,000 |
||
$240,000 |
||
$276,500 |
11 | ||
Machining cost | 210000 | |
/ Machine hours | 20000 | |
Activity rate for the machining activity | 10.50 | |
$10.50 per machine hour is correct option | ||
12 | ||
Number of machine hours | 5000 | |
X Activity rate for the machining activity | 10.50 | |
Machining cost assigned to A Product | 52500 | |
$52,500 is correct option | ||
13 | ||
Prime cost | 180000 | |
Setting up cost | 32000 | =120000*80/300 |
Ordering cost | 12000 | =90000*1200/9000 |
Machining cost | 52500 | |
Total product cost for A Product | 276500 | |
$276,500 is correct option |
Get Answers For Free
Most questions answered within 1 hours.