Question

THE FOLOWING INFORMATION IS USED FOR QUESTIONS 11 – 13. Test Company uses an activity-based cost...

  1. THE FOLOWING INFORMATION IS USED FOR QUESTIONS 11 – 13.

    Test Company uses an activity-based cost system and has identified the following overhead activities, estimated costs, cost drivers, and estimated usage for the coming period.

    Activity

    Estimated Cost

    Cost Driver

    Estimated Usage

    Setting up

    $120,000

    Number or setups

    300 setups

    Ordering

    90,000

    Number of orders

    9,000 orders

    Machining

         210,000

    Machine hours

    20,000 machine hours

    $420,000

    Test Company expects to use 10,500 direct labor hours for the period.

    The accounting records showed the following actual results for the production of A Product during the period

    A Product

    Prime cost

    $180,000

    Direct labor hours

    3,000

    Number of setups

    80

    Number of orders

    1,200

    Number of machine hours

    5,000

    Calculate the activity rate for the machining activity.

    $20 per direct labor hour

    $10.50 per machine hour

    $0.50 per direct labor hour

    $42 per machine hour

QUESTION 12

  1. THE FOLOWING INFORMATION IS USED FOR QUESTIONS 11 – 13.

    Test Company uses an activity-based cost system and has identified the following overhead activities, estimated costs, cost drivers, and estimated usage for the coming period.

    Activity

    Estimated Cost

    Cost Driver

    Estimated Usage

    Setting up

    $120,000

    Number or setups

    300 setups

    Ordering

    90,000

    Number of orders

    9,000 orders

    Machining

         210,000

    Machine hours

    20,000 machine hours

    $420,000

    Test Company expects to use 10,500 direct labor hours for the period.

    The accounting records showed the following actual results for the production of A Product during the period

    A Product

    Prime cost

    $180,000

    Direct labor hours

    3,000

    Number of setups

    80

    Number of orders

    1,200

    Number of machine hours

    5,000

    Calculate the machining cost assigned to A Product.

    $210,000

    $52,500

    $60,000

    $1,500

QUESTION 13

  1. THE FOLOWING INFORMATION IS USED FOR QUESTIONS 11 – 13.

    Test Company uses an activity-based cost system and has identified the following overhead activities, estimated costs, cost drivers, and estimated usage for the coming period.

    Activity

    Estimated Cost

    Cost Driver

    Estimated Usage

    Setting up

    $120,000

    Number or setups

    300 setups

    Ordering

    90,000

    Number of orders

    9,000 orders

    Machining

         210,000

    Machine hours

    20,000 machine hours

    $420,000

    Test Company expects to use 10,500 direct labor hours for the period.

    The accounting records showed the following actual results for the production of A Product during the period

    A Product

    Prime cost

    $180,000

    Direct labor hours

    3,000

    Number of setups

    80

    Number of orders

    1,200

    Number of machine hours

    5,000

    Calculate the total product cost for A Product.

    $96,500

    $390,000

    $240,000

    $276,500

Homework Answers

Answer #1
11
Machining cost 210000
/ Machine hours 20000
Activity rate for the machining activity 10.50
$10.50 per machine hour is correct option
12
Number of machine hours 5000
X Activity rate for the machining activity 10.50
Machining cost assigned to A Product 52500
$52,500 is correct option
13
Prime cost 180000
Setting up cost 32000 =120000*80/300
Ordering cost 12000 =90000*1200/9000
Machining cost 52500
Total product cost for A Product 276500
$276,500 is correct option
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at...
Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $   140000 500 orders Machine Setup Setups 315000 450 setups Machining Machine hours 1562500 125000 MH Assembly Parts 1240000 1000000 parts Inspection Inspections 320000 500 inspections If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is $0.14 per part. $280...
The company uses ABC and has determined the following activities, cost drivers and activity rates Activity...
The company uses ABC and has determined the following activities, cost drivers and activity rates Activity Center Activity Driver Activity rate Direct labor usage Direct labor hours $3 per DL hr Machine usage Machine hours $8 per machine hr Machine setups Setups $200 per set up Design changes Design changes $400 per design change You have completed Job 101. Determine the cost of Job 101, if the job required $1,000 in Direct Material, $3,000 in Direct Labor, 500 direct labor...
Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year:...
Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $441,280 Number of setups 560 Ordering costs 318,600 Number of orders 17,700 Machine costs 890,400 Machine hours 42,400 Receiving 294,000 Receiving hours 8,400 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $611,000 $832,000 Direct labor $481,000 $473,000 Units completed 15,400 8,300...
Activity Rates and Activity-Based Product Costing Hammer Company produces a variety of electronic equipment. One of...
Activity Rates and Activity-Based Product Costing Hammer Company produces a variety of electronic equipment. One of its plants produces two laser printers: the deluxe and the regular. At the beginning of the year, the following data were prepared for this plant: Deluxe Regular Quantity 100,000 800,000 Selling price $900 $750 Unit prime cost $529 $483 In addition, the following information was provided so that overhead costs could be assigned to each product: Activity Name Activity Driver Deluxe Regular Activity Cost...
PLEASE ANSWER ALL QUESTIONS AND SHOW YOUR WORK! Job 101 has a direct materials cost of...
PLEASE ANSWER ALL QUESTIONS AND SHOW YOUR WORK! Job 101 has a direct materials cost of $800 and a total manufacturing cost of $3,000. Overhead is applied to jobs at a rate of 150 percent of direct labor cost. What is the prime cost? ------------------------- Walnut Systems produces two different products, Product A, which sells for $124 per unit, and Product B, which sells for $196 per unit, using three different activities: Design, which uses Engineering Hours as an activity...
Sheridan Industries has three activity cost pools and two products. It estimates production 2,000 units of...
Sheridan Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Sheridan accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Activity Cost Pools Cost Drivers Estimated Overhead Estimated Use of Cost Drivers per Activity Product BC113 Product AD908 Machine setup...
Activity Rates and Activity-Based Product Costing Hammer Company produces a variety of electronic equipment. One of...
Activity Rates and Activity-Based Product Costing Hammer Company produces a variety of electronic equipment. One of its plants produces two laser printers: the deluxe and the regular. At the beginning of the year, the following data were prepared for this plant: Deluxe Regular Quantity 100,000 800,000 Selling price $900 $750 Unit prime cost $529 $483 In addition, the following information was provided so that overhead costs could be assigned to each product: Activity Name Activity Driver Deluxe Regular Activity Cost...
Plata Company has identified the following overhead activities, costs, and activity drivers for the coming year:...
Plata Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $120,000 Number of setups 300 Ordering costs 90,000 Number of orders 9,000 Machine costs 210,000 Machine hours 21,000 Plata produces two models of microwave ovens with the following activity demands: Model X Model Y Units completed 8,000 4,000 Number of setups 200 100 Number of orders 3,000 6,000 Machine hours 12,000 9,000 The company's...
Equally Accurate Reduced ABC System Silven Company has identified the following overhead activities, costs, and activity...
Equally Accurate Reduced ABC System Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $126,000 Number of setups 150 Ordering materials 18,000 Number of orders 900 Machining 126,000 Machine hours 10,500 Receiving 30,000 Receiving hours 1,250 Silven produces two models of cell phones with the following expected activity demands: Model X Model Y Units completed 5,000 10,000 Number of setups 100 50 Number...
1. Foxx Company incurs $410000 overhead costs each year in its three main departments, setup ($35000),...
1. Foxx Company incurs $410000 overhead costs each year in its three main departments, setup ($35000), machining ($265000), and packing ($110000). The setup department performs 40 setups per year, the machining department works 5000 hours per year, and the packing department packs 500 orders per year. Information about Foxx’s two products is as follows: Product A1 Product B1 Number of setups      20     20 Machining hours   1000 4000 Orders packed    150    350 Number of products manufactured    600    400 If machining hours...