Question

Streetside Construction decided to complete construction in 3 years. However, cutting back 1 year in construction...

Streetside Construction decided to complete construction in 3 years. However, cutting back 1 year in construction schedule means an increase in total estimated costs. Assume that at beginning of year 3 total estimated costs to complete the job in three years were revised to $35,000,000. Under the percentage of completion method, the loss for year three would be:

Homework Answers

Answer #1

No information regarding the percent of work already completed is given

Hence we can go by time based calculations

It was earlier fixed to complete the construction in 4 years however after cutting back 1 year Streetside construction has decided to finish it in 3 years

As no info regarding percentage of work finished is given we assume that 3/4 th of the work would have been completed by the end of third year if construction was for period of 4 years as decided initially

Based on time balance 25% of costs allocated for fourth year is now added back to 3rd year after rescheduling the time and balance 25% costs is the loss for 3rd year

So loss on based of percentage of completion for 3rd year=$35000000*3/4=$26250000

=$35000000-$26250000=$8750000

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
During 2019, Almon Inc. started a construction job with a contract price of $8000. The job...
During 2019, Almon Inc. started a construction job with a contract price of $8000. The job was completed in 2019 and information for the three years of construction is as follows: 2019 2020 2021 TOTAL costs incurred to date (ie sum of all costs, for all years, incurred at the end of the year) $2,000 $4,500 $7,600 Estimated costs to complete (as estimated at year end) 5,000 2900 -0- Billings to date 2,200 6,000 8,000 Collections to date 1,600 4,800...
During 2018, Miners Inc. started a construction job with a contract price of $20,000. The job...
During 2018, Miners Inc. started a construction job with a contract price of $20,000. The job was completed in 2020 and information for the three years of construction is as follows: Required: Using the PERCENTAGE-OF-COMPLETION (cost-to-cost) method: Show and label all calculations. (a)   Calculate the total percentage complete for the contract at the end of each year. Round the percentage complete to two decimal places (ie. 12.34%). (b) Calculate the amount of gross profit that Miners should be recognized each...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
Tamarisk Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Tamarisk Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $601,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $270,450 $492,820 $613,000 Estimated costs to complete 330,550 108,180 –0– Progress billings to date 273,000 550,000 903,000 Cash collected to date...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract price was $1,600,000. The Job was completed in 2018.                                                                                 2016                       2017                       2018 Costs incurred to date                                    400000                  935000                  1070000 Estimated costs to complete                       700000                  165000                  0 Billings to date                                                  300000                  900000                  1600000 Collections to date                                           270000                  810000                  1525000 Compute the amount of Gross Profit to be recognized for 2016 and 2017 assuming that ole is required to recognize revenue overtime. Compute the...
The board of directors of Ogle Construction Company is meeting to choose between the completed contract...
The board of directors of Ogle Construction Company is meeting to choose between the completed contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Ogle's controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: 1. Ogle commenced doing business on January 1, 2018. 2. Construction activities for the year ended December 31, 2018, were...
In 2013, Long Construction Corporation began construction work under a three-year contract. The contract price is...
In 2013, Long Construction Corporation began construction work under a three-year contract. The contract price is $2,400,000. Long uses the percentage-of-completion method for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2013, is as follows:   Balance Sheet   Accounts receivable (from construction progress billings) $ 38,000        Construction in progress $ 160,000        Less: Billings on construction contract (150,000 )        Cost of uncompleted contracts in excess of billings 10,000 Income Statement   Income (before tax) on the contract...
Widjaja Company is accounting for a long-term construction contract using percentage-of-completion method. It is a 4-year...
Widjaja Company is accounting for a long-term construction contract using percentage-of-completion method. It is a 4-year contract that is currently in its second year. The latest estimates of total contract costs indicate that the contract will be completed at a loss to Widjaja Company. a. What theoretical justification is there for Widjaja Company's use of the percentage-of-completion method? b. How would the company account for the projected loss?
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT