Question
The following data regarding the activity-based costing system
at the Company Co. is available:
Activity
Pool...
The following data regarding the activity-based costing system
at the Company Co. is available:
Activity
Pool
Base
Budgeted
Activity
Budgeted
Cost
Machine set up
# of setups
2710
$24804
Orders
# of orders
991
$96484
Shipping
Hours of shipping
time
2233
$41621
In addition, prior to adopting an activity based costing system,
Company Co. applied overhead based on direct labour hours. The
budgeted total labour hours for the year was 54645. If one job
required 424 direct labour hours, 39 setups, 50 orders, and 24
hours of shipping time what is the difference between the overhead
assigned using the traditional method and ABC?