Question

Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most...

Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Days Wait time 15.3 Inspection time 0.2 Process time 1.4 Move time 1.3 Queue time 2.5 Required: a. Compute the throughput time. (Round your answer to 1 decimal places.) b. Compute the manufacturing cycle efficiency (MCE). (Do not round intermediate calculations. Round your answer to nearest whole percentage.) c. What percentage of the production time is spent in non-value-added activities? (Do not round intermediate calculations. Round your answer to nearest whole percentage.) d. Compute the delivery cycle time. (Round your answer to 1 decimal place.)

Homework Answers

Answer #1

(a)-Throughput time

Throughput time = Inspection time + Process time + Move time + Queue time

= 0.2 days + 1.4 days + 1.3 days + 2.5 days

= 5.4 days

(b)-Manufacturing cycle efficiency (MCE)

Manufacturing cycle efficiency (MCE) = [Process time / Throughput time] x 100

= [1.4 Days / 5.4 Days] x 100

= 26%

(c)-Percentage of the production time is spent in non-value-added activities

Percentage of time spent on non-value-added activities = 100% – MCE%

= 100% – 26%

= 74%

(d)-Delivery cycle time.

Delivery cycle time = Wait time + Throughput time

= 15.3 Days + 5.4 Days

= 20.7 Days

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most...
Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Days Wait time 15.9 Inspection time 0.6 Process time 3.8 Move time 0.3 Queue time 3.2 Required: a. Compute the throughput time. (Round your answer to 1 decimal places.) b. Compute the manufacturing cycle efficiency (MCE). (Do not round intermediate calculations. Round your answer to nearest whole percentage.) c. What percentage of the production...
Pardun Corporation's management keeps track of the time it takes to process orders. During the most...
Pardun Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Pardun Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Days Wait time 13.2 Inspection time 0.7 Process time 1.60 Move time 0.6 Queue time 2.2 Required: a. Compute the throughput time.(Enter your answer rounded to 1 decimal...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.8 days Wait time (from order to start of production) 15.3 days Process time 3.3 days Move time 1.5 days Queue time 4.4 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.2 days Wait time (from order to start of production) 15.4 days Process time 3.3 days Move time 1.3 days Queue time 4.1 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:   Inspection time 0.4 days   Wait time (from order to start of production) 17.0 days   Process time 3.1 days   Move time 1.1 days   Queue time 4.2 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.3 days Wait time (from order to start of production) 16.0 days Process time 2.5 days Move time 1.5 days Queue time 3.7 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.5 days Wait time (from order to start of production) 16.2 days Process time 3.2 days Move time 1.5 days Queue time 4.0 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.7 days Wait time (from order to start of production) 15.7 days Process time 2.9 days Move time 0.8 days Queue time 3.6 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.3 days Wait time (from order to start of production) 16.7 days Process time 3.0 days Move time 1.5 days Queue time 3.7 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.5 days Wait time (from order to start of production) 15.9 days Process time 2.7 days Move time 1.2 days Queue time 3.5 days Required: 1. Compute the throughput time. (Round your answer to...