Question

Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the...

Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the fixtures. These activities and their associated budgeted activity costs and activity bases are as follows:


Activity
Budgeted
Activity Cost

Activity Base
Casting $250,900 Machine hours
Assembly 154,000 Direct labor hours
Inspecting 26,620 Number of inspections
Setup 43,120 Number of setups
Materials handling 45,120 Number of loads

Corporate records were obtained to estimate the amount of activity to be used by the two products. The estimated activity-base usage quantities and units produced follow:

Activity Base Entry Dining Total
Machine hours 5,110 4,540 9,650
Direct labor hours 4,400 6,600 11,000
Number of inspections 1,840 580 2,420
Number of setups 230 50 280
Number of loads 740 200 940
Units produced 10,200 5,100 15,300

a. Determine the activity rate for each activity. If required, round the rate to the nearest dollar.

Activity Activity Rate
Casting $ per machine hour
Assembly $ per direct labor hour
Inspecting $ per inspection
Setup $ per setup
Materials handling $ per load

b. Use the activity rates in (a) to determine the total and per-unit activity costs associated with each product. Round the per unit amounts to the nearest cent.

Product Total Activity Cost Activity Cost Per Unit
Entry Lighting Fixtures $ $
Dining Room Lighting Fixtures $ $

Homework Answers

Answer #1
a
Activity Activity rate
Casting 26 per machine hour =250900/9650
Assembly 14 per direct labor hour =154000/11000
Inspecting 11 per inspection =26620/2420
Setup 154 per setup =43120/280
Materials handling 48 per load =45120/940
b
Total Activity Cost Activity Cost Per Unit
Entry Lighting Fixtures 285640 28.00
Dining Room Lighting Fixtures 234120 45.91
Workings:
Entry Lighting Fixtures :
Casting 132860 =5110*26
Assembly 61600 =4400*14
Inspecting 20240 =1840*11
Setup 35420 =230*154
Materials handling 35520 =740*48
Total Activity Cost 285640
Divide by units 10200
Activity Cost Per Unit 28.00
Dining Room Lighting Fixtures :
Casting 118040 =4540*26
Assembly 92400 =6600*14
Inspecting 6380 =580*11
Setup 7700 =50*154
Materials handling 9600 =200*48
Total Activity Cost 234120
Divide by units 5100
Activity Cost Per Unit 45.91
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
BriteLite Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the...
BriteLite Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the fixtures. These activities and their associated activity costs and activity bases are as follows: Activity Activity Costs (Budgeted) Activity Base Casting $42,000 Machine hours Assembly 13,500 Direct labor hours Inspecting 5,800 Number of inspections Setup 16,800 Number of setups Materials handling 3,600 Number of loads Corporate records were obtained to estimate the amount of activity to be used by the two products. The estimated...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the fixtures. These activities and their associated budgeted activity costs and activity bases are as follows: Activity Budgeted Activity Cost Activity Base Casting $344,760 Machine hours Assembly 231,200 Direct labor hours Inspecting 38,080 Number of inspections Setup 33,360 Number of setups Materials handling 43,680 Number of loads Corporate records were obtained to estimate the amount of activity to be used by the two products. The...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the fixtures. These activities and their associated budgeted activity costs and activity bases are as follows: Activity Budgeted Activity Cost Activity Base Casting $215,740 Machine hours Assembly 203,110 Direct labor hours Inspecting 35,520 Number of inspections Setup 49,830 Number of setups Materials handling 46,280 Number of loads Corporate records were obtained to estimate the amount of activity to be used by the two products. The...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the fixtures. These activities and their associated budgeted activity costs and activity bases are as follows: Activity Budgeted Activity Cost Activity Base Casting $325,710 Machine hours Assembly 202,500 Direct labor hours Inspecting 33,150 Number of inspections Setup 36,480 Number of setups Materials handling 42,750 Number of loads Corporate records were obtained to estimate the amount of activity to be used by the two products. The...
Wings Co. budgeted $569,000 manufacturing direct wages, 2,500 direct labor hours, and had the following manufacturing...
Wings Co. budgeted $569,000 manufacturing direct wages, 2,500 direct labor hours, and had the following manufacturing overhead: Overhead Cost Pool Budgeted Overhead Cost Budgeted Level for Cost Driver Overhead Cost Driver Materials handling $ 184,000 4,600 pounds Weight of materials Machine setup 15,900 530 setups Number of setups Machine repair 1,200 30,000 machine hours Machine hours Inspections 21,000 300 inspections Number of inspections Requirements for Job #971 which manufactured 4 units of product: Direct labor 20 hours Direct materials 190...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $28 per machine hour Assembly $20 per direct labor hour Setup $75 per setup Inspecting $30 per inspection Production scheduling $12 per production order Purchasing $8 per purchase order The activity-base...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $33 per machine hour Assembly $18 per direct labor hour Setup $56 per setup Inspecting $20 per inspection Production scheduling $12 per production order Purchasing $8 per purchase order The activity-base...
Product costs using activity rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are...
Product costs using activity rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $25 per machine hour Assembly $32 per direct labor hour Setup $87 per setup Inspecting $15 per inspection Production scheduling $14 per production order Purchasing $5 per...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $30 per machine hour Assembly $15 per direct labor hour Setup $54 per setup Inspecting $32 per inspection Production scheduling $16 per production order Purchasing $13 per purchase order The activity-base...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $31 per machine hour Assembly $17 per direct labor hour Setup $46 per setup Inspecting $32 per inspection Production scheduling $18 per production order Purchasing $15 per purchase order The activity-base...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT