Krypton Ltd.’s budgeted information relating to the manufacture of two of its products is presented below:
# of times driver used |
||||
Activity |
Cost |
Driver |
Product A |
Product B |
Setup |
$64563 |
# of batches |
34 |
10 |
Engineering |
$115377 |
# of engineering hours |
6668 |
10233 |
Machine Maintenance |
$80361 |
# of machine hours |
7319 |
12666 |
Direct labour cost |
$12/hour |
$358659 |
$526086 |
|
Direct materials |
$125579 |
$90949 |
What is the total cost of Product B using Activity Based Costing?