Indiana Co. began a construction project in 2021 with a contract
price of $165 million to be received when the project is completed
in 2023. During 2021, Indiana incurred $32 million of costs and
estimates an additional $87 million of costs to complete the
project. Indiana recognizes revenue over time and for this project
recognizes revenue over time according to the percentage of the
project that has been completed.
In 2022, Indiana incurred additional costs of $52 million and
estimated an additional $39 million in costs to complete the
project. Indiana (Do not round your percentage
calculated):
A. Recognized revenue at 42 million gross profit on the project in 2022.
B. Recognized revenue at 7 million gross profit on the project in 2022
C. Recognized revenue at 40.50 million gross profit on the project in 2022
D Recognized revenue at 16.31 million gross profit on the project in 2022
Answer: | ||
Particulars | 2021 (in $ million ) | 2022 (in $ million ) |
Contract Price (P) | $165 | $165 |
Cost Incurred to Date (A) | $32 |
$84 ($32 + $52) |
Estimated cost to be incurred to complete the contract (B) |
$87 | $39 |
Total Cost ( C ) = A + B | $119 | $123 |
Percentage of Completion D = ( A / C ) x 100 | 26.89% | 68.29% |
Revenue to date ( D x P) | $44.37 | $112.68 |
Revenue of Previous year | - | ($44.37) |
Net Revenue this year ( E) | $44.37 | $68.31 |
Cost to date | $32 |
$84 ($32 + $52) |
Cost to date of previous year | - | $32 |
Net Cost for the year (F) | $32 | $52 |
Gross Profits (E - F) | $12.37 | $16.31 |
From given options, option (d) is
correct i.e., Recognized revenue at 16.31 million gross profit on the project in 2022 |
Get Answers For Free
Most questions answered within 1 hours.