Question

Red & Blue Corporation signs a contract at the beginning of 2020 to build a road...

Red & Blue Corporation signs a contract at the beginning of 2020 to build a road for the government.  Constructionwill take four years.  The following information is available on the contract.  

Total revenue =           $ 15,000,000

Total expected cost =       $ 12,000,000

Cost incurred during 2020 = $   4,500,000

If Red & Blue Corporation uses the prorata method, then how much revenue will the company recognize from the project for the year 2020?

a.

None

b.

$3,750,000

c.

$4,750,000

d.

$5,625,000

Homework Answers

Answer #1

For Red & Blue Corporation

Calculation of the Revenue to be Recognised from the project for the year 2020 using Pro rata Method:

Total Revenue = $15,000,000

Total Expected Cost = $12,000,000

Cost Incurred during 2020 = $4,500,000

Percentage Completion = (Cost Incurred during 2020/ Total Expected Cost) * 100

Percentage Completion = ($4,500,000 / $12,000,000) * 100 = 37.5%

Revenue to be Recognised = Total Revenue * Percentage Completion

Revenue to be Recognised = $15,000,000 * 37.5% = $5,625,000 (Option D)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Red & Blue Corporation signs a contract at the beginning of 2020 to build a road...
Red & Blue Corporation signs a contract at the beginning of 2020 to build a road for the government.  Construction will take four years.  The following information is available on the contract.   Total revenue =           $ 15,000,000 Total expected cost =       $ 12,000,000 Cost incurred during 2020 = $   4,500,000 If Red & Blue Corporation uses the prorata method, then how much revenue will the company recognize from the project for the year 2020? a. None b. $3,750,000 c....
On December 31, 2019, Shawshank Construction Inc. signs a contract to manufacture a bridge which it...
On December 31, 2019, Shawshank Construction Inc. signs a contract to manufacture a bridge which it anticipates the construction will take three years. The company’s accountants provide the following contract details relating to the project: Contract price: $780 million Estimated construction costs: $600 million Estimated total profit: $180 million During the three-year construction period, Shawshank incurred costs as follows: 2020 $ 60 million 2021 $360 million 2022 $180 million Shawshank uses the cost-to-cost method to recognize revenue. Which of the...
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building....
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building. Lion estimated that the total cost would be $ 320,000. Construction started immediately because the required completion date was August 31, 2021. Lion’s relevant data relating to this construction project were as follows:      2020             2021 Actual costs incurred $ 120,000      $ 204,000 Estimated costs to complete 200,000               -0- Progress billings 112,000        248,000 Collections 110,000        250,000 Instructions (show all supporting calculations) Calculate how much...
On December 31, 2019, Mass Construction Inc. signs a contract with the state of Massachusetts Department...
On December 31, 2019, Mass Construction Inc. signs a contract with the state of Massachusetts Department of Transportation to manufacture a bridge over the Merrimack. Mass Construction anticipates the construction will take three years. The company's accountants provide the following contract details relating to the project: Contract price $520 million Estimated construction costs $300 million Estimated total profit $220 million During the three-year construction period, Tri-State incurred costs as follows: 2020 $ 60 million 2021 $150 million 2022 $ 90...
On December 31 of the current year, State Construction Inc. signs a contract with the state...
On December 31 of the current year, State Construction Inc. signs a contract with the state of West Virginia Department of Transportation to manufacture a bridge over the New River. State Construction anticipates the construction will take three years. The company’s accountants provide the following contract details relating to the project: Contract price $624 million Estimated construction costs $480 million Estimated total profit $144 million During the three-year construction period, State Construction incurred costs as follows: Year 1 $48 million...
4. Financial Software Inc. (FSI) provides ERP software to large corporations.   Big Corporation signs a contract with...
4. Financial Software Inc. (FSI) provides ERP software to large corporations.   Big Corporation signs a contract with FSI on January 1, 2018.  FSI will provide the ERP, including installation and testing, consulting services to integrate the software with all of Big Corp’s other systems and 3 years of support services.  Another firm could provide the support services, but FSI requires that they perform the installation and testing. The total price of the contract is $2,400,000. FSI would charge $1,800,000 for the software (including...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017     $35 million Construction in progress (as of 12/31/2017)                                                                                                    $50 million Accounts Receivable from construction billings (as...
In 2017, Chicago Construction began work on a three-year construction project to build a new performing...
In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017                                                                                                                                                              $35 million Construction in progress (as of 12/31/2017)                                                                                                   $50 million Accounts Receivable from construction billings (as of...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Beth R. Jordan lives at 2322 Skyview Road, Mesa, AZ 85201. She is a tax accountant...
Beth R. Jordan lives at 2322 Skyview Road, Mesa, AZ 85201. She is a tax accountant with Mesa Manufacturing Company, 1203 Western Avenue, Mesa, AZ 85201 (employer identification number 11-1111111). She also writes computer software programs for tax practitioners and has a part-time tax practice. Beth is single and has no dependents. Beth was born on July 4, 1972, and her Social Security number is 123-45-6789. She wants to contribute $3 to the Presidential Election Campaign Fund. The following information...