Question

Southlake Inc uses the high low method to analyze cost behavior. The company observed that at...

Southlake Inc uses the high low method to analyze cost behavior. The company observed that at 30,000 machine hours of activity, total maintenece costs averaged $11/hour. When activity jumped to 60,000 machine hours which was still within the relevant range, the average total maintence cost was $9.

What are the total costs estimated to be at the level of 50,000 machine hours?

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Uninder Company uses the high-low method to estimate the cost function. The information for 2015 is...
Uninder Company uses the high-low method to estimate the cost function. The information for 2015 is provided below:                                                                 Machine-hours       Labor Costs       Highest observation of cost driver                 550                   $22,000       Lowest observation of cost driver                  250                  $ 13,000 What is the estimated total cost when 400 machine-hours are used?    a. $17,500     b. $29,000     c. $16,000     d. $20,800
Pearson Electric Company uses the high-low method to analyze mixed costs. The following information relates to...
Pearson Electric Company uses the high-low method to analyze mixed costs. The following information relates to the production data for the first six months of the year. Month Cost(Y) Hours(H) January $ 8,620 425 February $ 10,500 840 March $ 8,640 520 April $ 8,860 440 May $ 10,780 1,145 June $ 10,230 815 What is the estimated total cost at an operating level of 1,180 hours, using the high-low method? (Round variable cost per unit to 2 decimal places.)...
The Macon Company uses the high-low method to determine its cost equation. The following information was...
The Macon Company uses the high-low method to determine its cost equation. The following information was gathered for the past year: Machine Hours Direct Labor Costs Busiest month (June) 14,000 $ 200,000 Slowest month (December) 6,000 $ 120,000 If Macon expects to use 10,000 machine hours next month, what are the estimated direct labor costs? $160,000. $175,000. $180,000. $150,000.
Pearson Electric Company uses the high-low method to analyze mixed costs. The following information relates to...
Pearson Electric Company uses the high-low method to analyze mixed costs. The following information relates to the production data for the first six months of the year. Month Cost(Y) Hours(H) January $ 8,350 365 February $ 10,000 800 March $ 8,240 480 April $ 8,360 400 May $ 10,510 1,085 June $ 9,750 775 How should the cost function be properly stated using the high-low method?
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of...
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 51,000 $ 181,360 May 41,000 $ 157,760 June 61,000 $ 204,960 July 71,000 $ 228,560 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) $ 53,300 Supervisory salaries (fixed) 48,000 Maintenance (mixed) 56,460...
Wayside Company has machine hours of 5,000 and machine costs ofS170,000 at the high data point....
Wayside Company has machine hours of 5,000 and machine costs ofS170,000 at the high data point. Machine hours are 2,000 and machine costs are S110,000 at the low data point. Wayside uses the high-low method to estimate costs. 1.Refer to Exhibit 5-4. What is the estimated cost per machine hour?     $34     $55     $20     $40     None of the answer choices is correct. 2.Refer to Exhibit 5-4. What is the estimated total fixed cost?    $60,000     $140,000     $55,000     $70,000     None of the answer choices...
Relevant Range and High-Low Method The following selected data relate to the major cost categories experienced...
Relevant Range and High-Low Method The following selected data relate to the major cost categories experienced by Shaw Company at varying levels of operating volumes. Assuming that all operating volumes are within the relevant range, calculate the appropriate costs in each column in which blanks appear: Total Cost (@ 3,000 Units) Total Cost (@ 4,000 units) Variable Cost per Unit Total Fixed Cost Total Cost (@ 5,000 units) Direct labor (variable) $63,000 $84,000 $Answer $Answer $Answer Factory supervision (semi-variable) 50,000...
High-Low Method, Cost Formulas The controller of the South Charleston plant of Ravinia, Inc., monitored activities...
High-Low Method, Cost Formulas The controller of the South Charleston plant of Ravinia, Inc., monitored activities associated with materials handling costs. The high and low levels of resource usage occurred in September and March for three different resources associated with materials handling. The number of moves is the driver. The total costs of the three resources and the activity output, as measured by moves for the two different levels, are presented as follows: Resource        Number of Moves        Total...
High-Low Method, Cost Formulas The controller of the South Charleston plant of Ravinia, Inc., monitored activities...
High-Low Method, Cost Formulas The controller of the South Charleston plant of Ravinia, Inc., monitored activities associated with materials handling costs. The high and low levels of resource usage occurred in September and March for three different resources associated with materials handling. The number of moves is the driver. The total costs of the three resources and the activity output, as measured by moves for the two different levels, are presented as follows: Resource        Number of Moves        Total...
High-Low Method, Cost Formulas The controller of the South Charleston plant of Ravinia, Inc., monitored activities...
High-Low Method, Cost Formulas The controller of the South Charleston plant of Ravinia, Inc., monitored activities associated with materials handling costs. The high and low levels of resource usage occurred in September and March for three different resources associated with materials handling. The number of moves is the driver. The total costs of the three resources and the activity output, as measured by moves for the two different levels, are presented as follows: Resource        Number of Moves        Total...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT