Question

Madtack Company uses a job-order costing system and started the month of March with three jobs...

Madtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #359 Job #360 Job #361 beginning work in process ..... $4,800 $6,300 $3,500 COSTS ADDED DURING MARCH direct materials .............. $3,300 $4,100 $4,600 direct labor .................. 5,000 3,000 4,000 Madtack applies overhead to jobs at a rate of 70% of direct materials used. During March, Madtack completed and sold Job #360. Job #361 was also completed but was not sold by the end of March. Job #359 was not completed by the end of March. Madtack's actual overhead cost for the month of March totaled $9,500. Calculate Madtack's cost of goods sold for March after the overhead variance is closed.

Homework Answers

Answer #1
Job 359 Job 360 Job 361 Total
Beginning Work in process 4800 6300 3500 14600
Add:
Direct Material 3300 4100 4600 12000
Direct Labor 5000 3000 4000 12000
Applied Overhead(70%*DM) 2310 2870 3220 8400
Total cost 15410 16270 15320 47000
Overhead applied 8400
Actual Overhead 9500
Overapplied Overhead -1100
Job 360 completed and sold
Unadjusted Cost of Good Sold 16270
Less : Overapplied Overhead -1100
Adjusted Cost of Good Sold 17370
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Madtack Company uses a job-order costing system and started the month of March with three jobs...
Madtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #359 Job #360 Job #361 beginning work in process ..... $4,800 $6,300 $3,500 COSTS ADDED DURING MARCH direct materials .............. $3,300 $4,100 $4,600 direct labor .................. 5,000 3,000 4,000 Madtack applies overhead to jobs at a rate of 70% of direct materials used. During March,...
Madtack Company uses a job-order costing system and started the month of March with only one...
Madtack Company uses a job-order costing system and started the month of March with only one job in process (Job #359). This job had $5,000 of total cost assigned to it at the beginning of March. Madtack applies overhead to jobs at a rate of 175% of direct labor cost. During March, Madtack assigned production costs as follows to the jobs worked on during the month: Job #359 Job #360 Job #361 direct materials .......... $1,000 $5,000 $3,000 direct labor...
Madtack Company uses a job-order costing system and started the month of March with only one...
Madtack Company uses a job-order costing system and started the month of March with only one job in process (Job #359). This job had $5,000 of total cost assigned to it at the beginning of March. Madtack applies overhead to jobs at a rate of 175% of direct labor cost. During March, Madtack assigned production costs as follows to the jobs worked on during the month: Job #359 Job #360 Job #361 direct materials .......... $1,000 $5,000 $3,000 direct labor...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
enkins Company uses a job order cost system with overhead applied to jobs on the basis...
enkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Br3-Pf Company uses a job-order costing system and applies overhead costs to jobs using a plant-wide...
Br3-Pf Company uses a job-order costing system and applies overhead costs to jobs using a plant-wide rate of 90% of direct materials cost. Br3-Pf Company began work on four jobs during June. Information related to the four jobs appears below: Job #1 Job #2 COSTS ADDED DURING JUNE direct materials .............. $5,800 $7,500 direct labor .................. $7,300 $6,300 Job #3 Job #4 COSTS ADDED DURING JUNE direct materials .............. $8,200 $6,400 direct labor .................. $7,920 $7,560 By the end of...
Jackson Company applies overhead to products using a pre determined rate of $12.10 per direct labor...
Jackson Company applies overhead to products using a pre determined rate of $12.10 per direct labor hour. During 2019, Jackson Company began work on three jobs. Information relating to these three jobs appears below: Job #359 Job #360 Job #361 direct materials ....... $98,000 $75,000 $91,000 direct labor cost ...... $95,200 $79,900 $69,700 direct labor hours ..... 5,600 4,700 4,100 By the end of 2019, job #359 and job #361 had been completed. Job #360 was not completed by the...
Jackson Company applies overhead to products using a pre determined rate of $12.10 per direct labor...
Jackson Company applies overhead to products using a pre determined rate of $12.10 per direct labor hour. During 2019, Jackson Company began work on three jobs. Information relating to these three jobs appears below: Job #359 Job #360 Job #361 direct materials ....... $98,000 $75,000 $91,000 direct labor cost ...... $95,200 $79,900 $69,700 direct labor hours ..... 5,600 4,700 4,100 By the end of 2019, job #359 and job #361 had been completed. Job #360 was not completed by the...