Perit Industries has $140,000 to invest. The company is trying to decide between two alternative uses of the funds. The alternatives are:
Project A | Project B | |||
Cost of equipment required | $ | 140,000 | $ | 0 |
Working capital investment required | $ | 0 | $ | 140,000 |
Annual cash inflows | $ | 23,000 | $ | 35,000 |
Salvage value of equipment in six years | $ | 8,400 | $ | 0 |
Life of the project | 6 years | 6 years |
The working capital needed for project B will be released at the end of six years for investment elsewhere. Perit Industries’ discount rate is 15%.
Click here to view Exhibit 13B-1 and Exhibit 13B-2, to determine the appropriate discount factor(s) using tables.
Required:
1. Compute the net present value of Project A. (Enter negative values with a minus sign. Round your final answer to the nearest whole dollar amount.)
2. Compute the net present value of Project B. (Enter negative values with a minus sign. Round your final answer to the nearest whole dollar amount.)
3. Which investment alternative (if either) would you recommend that the company accept?
Answer:
Computation of NPV:
Project A:
Year | Cashflows | PVIF/PVIFA @ 15% | Present value of cash flows |
0 | ($140,000) | 1 | ($140,000) |
1-6 | $23,000 | 3.7845 | $87,043.50 |
6 | $8,400 | 0.4323 | $3,631.32 |
NPV | ($49,325.18) |
Project B:
Year | Cashflows | PVIF/PVIFA @ 15% | Present value of cash flows |
0 | ($140,000) | 1 | ($140,000) |
1-6 | $35,000 | 3.7845 | $132,457.50 |
6 | $140,000 | 0.4323 | $60,522 |
NPV | $52,979.50 |
As per NPV basis, investor should accept Project B which gives positive NPV.
Note: In Project B in the Year 6 cash flows are working capital realised amount of $140000
Get Answers For Free
Most questions answered within 1 hours.