Question

Activity-Based Budget Macon Industries has the following budget information available for February: Units manufactured 30,000 Factory...

Activity-Based Budget
Macon Industries has the following budget information available for February:

Units manufactured 30,000
Factory administration $60,000
Assembly 0.5 hour per unit X $12
Direct materials 2 pounds per unit X $7
Inspection $600 per batch of 1,000 units
Manufacturing overhead $7 per unit
Product development $20,000
Setup cost $14 per batch of 1,000 units


Use activity based costing to prepare a manufacturing cost budget for February. Clearly distinguish between unit, batch, and facility-level costs.

Macon Industries
Activity-Based Manufacturing Cost Budget
For the Month of February
Unit-level costs:
Direct materials
Assembly
Factory administrationInspectionManufacturing overheadProduct development
Batch-level costs:
Setup
Factory administrationInspectionManufacturing overheadProduct development
Product-level costs:
Factory administrationInspectionManufacturing overheadProduct development
Facility-level costs:
Factory administrationInspectionManufacturing overheadProduct development
Budgeted manufacturing costs

Homework Answers

Answer #1

Answer-

MACON INDUSTRIES
ACTIVITY-BASED MANUFACTURING COST BUDGET
FOR THE MONTH OF FEBRUARY
PARTICULARS AMOUNT
$
Unit-level costs:-
Direct materials (30000 units*2 pounds per unit)*$7 per pound 420000
Assembly (30000 units*0.5 hours per unit)*$12 per pound 180000
Manufacturing overhead 30000 units*$7 per unit 210000
Batch-level costs:-
Set up (30000 units/1000 units)*$14 per batch 420
Inspection (30000 units/1000 units)*$600 per batch 18000
Product-level costs:-
Product development 20000
Facility-level costs:-
Factory administration 60000
Budgeted manufacturing costs $908420
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Activity-Based Budget Highlands Industries has the following budget information available for February: Units manufactured 25,000 Factory...
Activity-Based Budget Highlands Industries has the following budget information available for February: Units manufactured 25,000 Factory administration $145,000 Assembly 0.25 hour per unit X $20 Direct materials 3 pounds per unit X $6 Inspection $40 per batch of 1,000 units Manufacturing overhead $8 per unit Product development $50,000 Setup cost $100 per batch of 1,000 units Use activity-based costing to prepare a manufacturing cost budget for February. Clearly distinguish between unit, batch, and facility-level costs. HighlandsIndustries Activity-Based Manufacturing Cost Budget...
Activity-Based Costing: Factory Overhead Costs The total factory overhead for Bardot Marine Company is budgeted for...
Activity-Based Costing: Factory Overhead Costs The total factory overhead for Bardot Marine Company is budgeted for the year at $1,344,900, divided into four activities: fabrication, $672,000; assembly, $234,000; setup, $239,400; and inspection, $199,500. Bardot Marine manufactures two types of boats: speedboats and bass boats. The activity-base usage quantities for each product by each activity are as follows: FabricationAssemblySetupInspection Speedboat10,500dlh29,250dlh76setups131inspections Bass boat31,500 9,750 554 919 42,000dlh39,000dlh630setups1,050inspections Each product is budgeted for 4,000 units of production for the year. a.   Determine the...
Activity-Based Costing: Factory Overhead Costs The total factory overhead for Bardot Marine Company is budgeted for...
Activity-Based Costing: Factory Overhead Costs The total factory overhead for Bardot Marine Company is budgeted for the year at $925,250, divided into four activity pools: fabrication,, $459,000; assembly, $203,000; setup, $141,750; and inspection, $121,500. Bardot Marine manufactures two types of boats: speedboats and bass boats. The activity-base usage quantities for each product by each activity are as follows: Fabrication Assembly Setup Inspection Speedboat 6,750 dlh 21,750 dlh 49 setups 84 inspections Bass boat 20,250 7,250 356 591 27,000 dlh 29,000...
Activity-Based Costing: Factory Overhead Costs The total factory overhead for Bardot Marine Company is budgeted for...
Activity-Based Costing: Factory Overhead Costs The total factory overhead for Bardot Marine Company is budgeted for the year at $1,243,200, divided into four activities: fabrication, $608,000; assembly, $248,000; setup, $211,200; and inspection, $176,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The activity-base usage quantities for each product by each activity are as follows: Fabrication Assembly Setup Inspection Speedboat 8,000 dlh 23,250 dlh 58 setups 100 inspections Bass boat 24,000 7,750 422 700 32,000 dlh 31,000 dlh...
ack Inc. manufactures two products and uses an activity-based costing system. Jack currently classifies machine setup...
ack Inc. manufactures two products and uses an activity-based costing system. Jack currently classifies machine setup costs of $120,000 as batch-level. Product A Product B Units 50,000 75,000 Batches 100 400 Direct Materials $10 per unit $10 per unit Direct Labour $15 per unit $15 per unit What will be the effect on the unit cost of Product A if Jack classifies the machine setup costs as product-level? Select one: a. It will decrease by $0.72 b. It will increase...
Tangshang Industries production budget from the 2nd quarter of 2018, projected the following amounts of units...
Tangshang Industries production budget from the 2nd quarter of 2018, projected the following amounts of units to be produced: April    1,000 units May     1,200 units June     1,250 units Each unit requires 2 parts of component A and 3 parts of component B. Component A cost is $1.25 per unit and component B cost is $.80 per unit. 1.Calculate the Direct Material budgeted cost for May 2018 2.Calculate the Direct Material budgeted cost for the quarter April - June 2018...
Zeus Industries manufactures two types of electrical power units, custom and standard, which involve four factory...
Zeus Industries manufactures two types of electrical power units, custom and standard, which involve four factory overhead activities—production setup, procurement, quality control, and materials management. An activity analysis of the overhead revealed the following estimated activity costs and activity bases for these activities: Activity Activity Cost Activity Base Production setup $ 81,000 Number of setups Procurement 145,000 Number of purchase orders (PO) Quality control 188,500 Number of inspections Materials management 80,000 Number of components Total $494,500 The activity-base usage quantities...
Activity-Based Costing: Factory Overhead Costs The total factory overhead for Bardot Marine Company is budgeted for...
Activity-Based Costing: Factory Overhead Costs The total factory overhead for Bardot Marine Company is budgeted for the year at $1,296,900, divided into four activities: fabrication, $680,000; assembly, $248,000; setup, $198,900; and inspection, $170,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The activity-base usage quantities for each product by each activity are as follows: Fabrication Assembly Setup Inspection Speedboat 8,500 dlh 23,250 dlh 61 setups 106 inspections Bass boat 25,500 7,750 449 744 34,000 dlh 31,000 dlh...
Tangshang Industries production budget from the 2nd quarter of 2018, projected the following amounts of units...
Tangshang Industries production budget from the 2nd quarter of 2018, projected the following amounts of units to be produced: April 1,000 units May    1,200 units June    1,250 units Each unit requires 2 parts of component A and 3 parts of component B. Component A cost is $1.25 per unit and component B cost is $.80 per unit. Each unit requires the following labor: 2 hours in the processing department 1 hour in the assembly department Processing department labor rate is...
A company has prepared a master budget for the month of February when they expected to...
A company has prepared a master budget for the month of February when they expected to sell 4,000 units. They actually sold 3,750 units. Calculate the flexible budget and the spending and volume variances for February. Identify if the variances are favorable or unfavorable. Actual Costs 3,750 Units Spending Variances Flexible Budget _______Units Volume Variances Master Budget 4,000 Units Manufacturing Costs: Direct Materials $14,500 $16,000 Direct Labor 38,500 40,000 Variable Manufacturing Overhead 12,000 14,000 Fixed Manufacturing Overhead 20,000 21,000 Total...