Velshi Printers has contracts to complete weekly supplements required by forty-six customers. For the year 2018, manufacturing overhead cost estimates total $1,760,000 for an annual production capacity of 16 million pages.
For 2018 Velshi Printers has decided to evaluate the use of additional cost pools. After analyzing manufacturing overhead costs, it was determined that number of design changes, setups, and inspections are the primary manufacturing overhead cost drivers. The following information was gathered during the analysis:
Cost pool Manufacturing overhead costs Activity level
Design changes $160,000 200 design changes
Setups 1,530,000 5,000 setups
Inspections 70,000 7,000 inspections
Total manufacturing overhead costs $1,760,000
During 2018, two customers, Money Managers and Hospital Systems, are expected to use the following printing services:
Activity Money Managers Hospital Systems
Pages 60,000 76,000
Design changes 14 0
Setups 16 6
Inspections 25 33
Assuming activity-cost pools are used, what are the activity-cost driver rates for design changes, setups, and inspections cost pools?
A. |
$800.00 per change, $306.00 per setup, $10.00 per inspection |
|
B. |
$22.86 per change, $306.00 per setup, $350 per inspection |
|
C. |
$32.00 per change, $10.00 per setup, $306.00 per inspection |
|
D. |
$800.00 per change, $14.00 per setup, $218.57 per inspection |
Correct Option A | |||||
Working Note : | |||||
Note 1: Overhead allocation sheet | |||||
Activity | Total OH Cost | Total Cost Driver | Activity Rate | ||
Design Changes | 160,000 | 200 | 800.00 | Per change | (total cost of activity/No. of Activity) |
SetUps | 1,530,000 | 5000 | 306.00 | Per setup | (total cost of activity/No. of Activity) |
Inspections | 70,000 | 7000 | 10.00 | Per inspection | (total cost of activity/No. of Activity) |
Total | 1,760,000 | ||||