Question

Finn Ltd., a manufacturer of cars, applies overhead based on direct labour hours. For 20x3, total...

Finn Ltd., a manufacturer of cars, applies overhead based on direct labour hours. For 20x3, total overhead is estimated to be $1608428 and total direct labour hours are estimated to be 158990.

Finn is working on Job 24, which currently has $32642 in direct materials and 480 hours (at a rate of $16 per hour) of direct labour attached to it. Below is the expected costs to complete the job:

Direct materials

$17399

Direct labour hours

538 hours


What is the total expected cost for Job 24?

Homework Answers

Answer #1

Overhead Rate= Total overhead/ Total Direct labour hours

=$1608428/$158990=$ 10.12/direct labour hr (approx)

Cost incurred till date (A) Cost to be incurred to complete the job (B) Total Expected Cost (A+B)
Direct Material $32642 $17399 $50041
Direct Labour 480×$16=$7680 538×$16=$8608 $16288
Overhead 480×10.12=$4857.6 538×10.12=$5444.56 $10302.16
Total $76631.16

Please give your feedback!! Happy Learning :)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Dayflight applies overhead based on direct labour dollars in their Assembly Division. The company has budgeted...
Dayflight applies overhead based on direct labour dollars in their Assembly Division. The company has budgeted 50,000 direct labour hours at a cost of $10 per hour and manufacturing overhead of $750,000 in the Assembly Division for the year. What is the Assembly Division’s predetermined overhead rate for the year? A. $15.00 per direct labour dollar. B. $10.00 per direct labour dollar. C*. $ 1.50 per direct labour dollar. D. $ 0.67 per direct labour dollar. E. $ 0.07 per...
Waymire Ltd. manufactures two products and currently allocates overhead based on direct labour hours. For the...
Waymire Ltd. manufactures two products and currently allocates overhead based on direct labour hours. For the coming year, the company is considering changing to an activity based costing system by allocating overhead based on 3 activities. The estimated amount of overhead traceable to the 3 activities for the coming year are given below: Activity Cost driver Cost Product 1 Product 2 Purchase orders # of orders $881100 262 580 Maintenance Machine hours $408064 19261 17597 Inspection # of inspections $704263...
Waymire Ltd. currently uses a traditional costing system based on direct labour hours to allocate overhead....
Waymire Ltd. currently uses a traditional costing system based on direct labour hours to allocate overhead. This year, the company has budgeted to produce 1721 units of one of its products. Each unit requires 4 hours of direct labour. For the coming year, the company is considering changing to an activity based costing system by allocating overhead based on 3 activities. The following are the activities, budgeted total cost and cost drivers per activity for the upcoming year: Activity Cost...
A company began operations on January 1, 20x3. The company uses a job order system and...
A company began operations on January 1, 20x3. The company uses a job order system and started the following jobs during January 20x3: Job 101 Job 102 Job 103 Direct materials $18422 $24413 $35988 Direct labour hours 971 1387 737 Additional information is as follows: Total estimated overhead $302539 Total estimated direct labour hours 19248 Actual direct labour rate $19 per direct labour hour All three jobs were completed by the end of January 20x3. Finished goods at January 31,...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,900 units. Manufacturing overhead is budgeted at $124,600 for the period (20% of this cost is fixed). The 16,830 hours worked during the period resulted in the production of 8,240 units. The variable manufacturing overhead cost incurred was $101,200 and the fixed manufacturing overhead cost was $28,900. a.Calculate the variable overhead...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,600 units. Manufacturing overhead is budgeted at $120,400 for the period (20% of this cost is fixed). The 16,730 hours worked during the period resulted in the production of 8,190 units. The variable manufacturing overhead cost incurred was $98,300 and the fixed manufacturing overhead cost was $28,100. 1.Calculate the variable overhead...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,300 units. Manufacturing overhead is budgeted at $124,500 for the period (20% of this cost is fixed). The 16,290 hours worked during the period resulted in the production of 8,000 units. The variable manufacturing overhead cost incurred was $100,800 and the fixed manufacturing overhead cost was $28,400. Calculate the variable overhead...
Nguyen Inc. applies overhead to products based on direct labor hours using normal costing. During 2016,...
Nguyen Inc. applies overhead to products based on direct labor hours using normal costing. During 2016, total overhead costs were estimated to be $500,000. Actual overhead totaled $540,000 based on 32,000 actual direct labor hours. At the end of the year, overhead was overapplied by $20,000. Based on this information, what was the predetermined overhead rate used during 2016? $16.88 per direct labor hour. $16.25 per direct labor hour. $15.63 per direct labor hour. $17.50 per direct labor hour. None...
Beckner Inc. is a job-order manufacturer. The company uses a predetermined overhead rate based on direct...
Beckner Inc. is a job-order manufacturer. The company uses a predetermined overhead rate based on direct labor hours to apply overhead to individual jobs. For the current year, estimated direct labor hours are 133,000 and estimated factory overhead is $784,700. The following information is for September. Job X was completed during September, while Job Y was started but not finished. September 1, inventories:     Materials $24,000     Work-in-process (All Job X) 53,400     Finished goods 105,600 Materials purchases $157,000 Direct materials requisitioned:     Job...
Swifty Company applies manufacturing overhead based on direct labor hours. Information concerning manufacturing overhead and labor...
Swifty Company applies manufacturing overhead based on direct labor hours. Information concerning manufacturing overhead and labor for the year as follows: Actual manufacturing overhead $167400 Estimated manufacturing overhead $159600 Direct labor incurred 2700 hours @ $25 = $67500 Direct labor estimated 2800 hours @ $24 = $67200 How much is over or underapplied overhead at year end? $7800 overapplied. $13500 underapplied. $5700 underapplied. $6200 underapplied.