Finn Ltd., a manufacturer of cars, applies overhead based on direct labour hours. For 20x3, total overhead is estimated to be $1608428 and total direct labour hours are estimated to be 158990.
Finn is working on Job 24, which currently has $32642 in direct materials and 480 hours (at a rate of $16 per hour) of direct labour attached to it. Below is the expected costs to complete the job:
Direct materials |
$17399 |
Direct labour hours |
538 hours |
What is the total expected cost for Job 24?
Overhead Rate= Total overhead/ Total Direct labour hours
=$1608428/$158990=$ 10.12/direct labour hr (approx)
Cost incurred till date (A) | Cost to be incurred to complete the job (B) | Total Expected Cost (A+B) | |
Direct Material | $32642 | $17399 | $50041 |
Direct Labour | 480×$16=$7680 | 538×$16=$8608 | $16288 |
Overhead | 480×10.12=$4857.6 | 538×10.12=$5444.56 | $10302.16 |
Total | $76631.16 |
Please give your feedback!! Happy Learning :)