Calculate the OEE for a plant that operates as follows:
- 3 Shifts of 8 hours each
- Shift 3 is not operating for a while
- Lunch break per shift = 30 minutes
- Service Talk: 10 minutes per shift
- Set up per shift : 75 minutes
- Breakdown Shift 1 = 75 minutes
- Breakdown Shift 2 = 65 minutes
- Speed Losses (idle & minor losses) ; 225 minutes
- Time used to create (make) defects = 56 minutes
Based on question only availability ratio can be calculated. Which is 38.02%
For calculations of OEE provide actual production and Defects produced in a day also