Question

ABC uses activity based costing where overhead from three different production departments are allocated to products...

ABC uses activity based costing where overhead from three different production departments are allocated to products as follows:

Activity - Driver - Activity Rate - Product A - Product B

Cutting - Machine Hours - $2.00 per machine hour - 2,000 hours - 3,000 hours

Assembly - Assembly Hours - $.50 per assembly hour - 3,000 hours - 5,000 hours

Painting - Gallons of Paint - $5.00 per gallon - 1,500 gallons - 1,300 gallons

Raw materials are directly followed to each product and the amount of raw materials used for Product A was $15,000 and for Product B was $12,000. Direct labor is directly followed to each product and the amount of direct labor used for product A was $5,000 and for product B was $7,000. There were 1,000 units of product A manufactured and 2,000 units of product B manufactured.

Calculate the total unit cost of making product A and product B using ABC. Show computations.

Homework Answers

Answer #1
CALCULATION OF UNIT COSTING AS PER ABC
Particulars Product A Product B
(1000 Units) (2000 Units)
Raw Material $15,000 $12,000
Direct Labour $5,000 $7,000
Prime Cost (A) $20,000 $19,000
Overhead Cost
Cutting Expenses (B) $4,000 $6,000
(2000 Hrs X $ 2.00 Per Hrs) (2000 Hrs X $ 3.00 Per Hrs)
Assempbly Expenses($ 5 Per Hrs) (,C) $1,500 $2,500
(3000 Hrs X $ 0.5 Per Hrs) (5000 Hrs X $ 0.5 Per Hrs)
Painting Expenses (D) $7,500 $6,500
(1500 Gallon X $ 5 Per Gallon) (1300 Gallon X $ 5 Per Gallon)
Total Unit Cost (A+B+C+D) $33,000 $34,000
Total Unit 1000 Units 2000 Units
Per Unit Cost $33 $17
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ABC uses activity based costing where overhead from three different production departments are allocated to products...
ABC uses activity based costing where overhead from three different production departments are allocated to products as follows: Activity                                     Driver                                        Activity Rate                                         Product A              Product B Cutting                                     Machine Hours                                     $2.00 per machine hour                                2,000 hours        3,000 hours Assembly              Assembly Hours                 $.50 per assembly hour                                   3,000 hours        5,000 hours Painting                 Gallons of Paint                                   $5.00 per gallon                                  1,500 gallons     1,300 gallons Raw materials are directly followed to each product and the amount of raw materials used for...
Part 1 ABC uses activity based costing where overhead from three different production departments are allocated...
Part 1 ABC uses activity based costing where overhead from three different production departments are allocated to products as follows: Activity                 Driver - Activity Rate - Product A - Product B Cutting Machine Hours - $2.00 per machine hour - 2,000 hours - 3,000 hours Assembly            Assembly Hours - $.50 per assembly hour - 3,000 hours - 5,000 hours Painting                Gallons of Paint - $5.00 per gallon - 1,500 gallons - 1,300 gallons Raw materials are directly followed to...
1. A company uses activity-based costing to determine the costs of its three products: A, B,...
1. A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 89,000 7,900 10,900 21,900 Activity 2 $ 64,000 8,900 16,900 9,900 Activity 3 $ 120,000 4,400 2,900 3,525 How much overhead will be assigned to Product...
ABC Manufacturing uses normal costing and allocates manufacturing overhead to jobs based on a budgeted direct...
ABC Manufacturing uses normal costing and allocates manufacturing overhead to jobs based on a budgeted direct labor-hour rate for the actual direct labor hours. Any overallocated or underallocated overhead is written-off to the cost of goods sold at the end of the month. During April 2019, ABC Manufacturing recorded the following: Budgeted manufacturing overhead costs: $400,000 Budgeted direct labor-hours: 20,000 DLHRS Budgeted machine hours: 16,000 MHRS Actual manufacturing overhead costs: $360,000 Actual direct labor-hours:   22,500 DLHRS Actual machine hours: 15,000...
A company uses activity-based costing to determine the costs of its three products: A, B, and...
A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 75,000 6,500 9,500 20,500 Activity 2 $ 50,000 7,500 15,500 8,500 Activity 3 $ 92,000 3,000 1,500 2,125 How much overhead will be assigned to Product B...
Q3.ABC corporation applying normal costing system has provided the following data from its activity-based costing system...
Q3.ABC corporation applying normal costing system has provided the following data from its activity-based costing system as follows: (Amounts in SAR)                                           [3 Marks] Activities Estimated Overhead Costs Expected Cost Drivers Quantities Cost Drivers Assembly 120,500 10,000 Number of Machine Hours Processing Orders 80,500 7,000 Number of Orders Inspection 75,500 5,000 Number of Inspection Hours Total 276,000 22,000 Actual Data concerning the company's product X appears below: Annual unit production and sales 500 units Annual machine hours 5,000 Annual number of...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000 setup hours) $118,000 Production scheduling (400 batches) 60,000 Production engineering (60 change orders) 150,000 Supervision (2,000 direct labor hours) 46,000 Machine maintenance (12,000 machine hours) 60,000 Total activity costs $434,000 The following additional data were provided for Job 845: Direct materials costs $7,000 Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) $1,000 Setup hours 5...
ABC Corporation uses activity-based costing to compute product margins. Overhead costs have already been allocated to...
ABC Corporation uses activity-based costing to compute product margins. Overhead costs have already been allocated to the company's three activity cost pools--Machining, Order Filling, and Other. The costs in those activity cost pools appear below: Machining $ 15,800 Order Filling $ 6,400 Other $ 9,800 Machining costs are assigned to products using machine-hours (MHs) and Order Filling costs are assigned to products using the number of orders. The costs in the Other activity cost pool are not assigned to products....
Oxnard Company uses a volume-based costing system that applies overhead cost based on machine hours at...
Oxnard Company uses a volume-based costing system that applies overhead cost based on machine hours at $25 per machine hour. The company is considering adopting an activity-based costing system with the following data: Activity Cost Driver Rate Materials handling Pounds of material $1.50 Lathe work Number of parts $1.00 Milling Number of machine hours $8.00 Grinding Number of turns $0.40 Testing Number of units tested $15.00 The two jobs processed in the month of May had the following characteristics: Job...
Hopscotch​ Limited, a manufacturer of a variety of​ products, uses an activity−based costing system. Information from...
Hopscotch​ Limited, a manufacturer of a variety of​ products, uses an activity−based costing system. Information from its system for the year for all products​ follows: Activity cost pool   Total cost Total activity Assembly $584,900 21,000 machine−hours Inspection $342,000 8,500 inspection−hours Packaging $24,600 1,400 order Hopscotch Limited makes 490 of its product B63 a​ year, which requires a total of 34 machine​ hours, 11 inspection​ hours, and 20 orders. Product B63 requires $45.70 in direct materials per unit and $57.20 in...