Question

Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow:
  

Month

Machine Hours

Electricity Costs

January

3,500

$

18,900

February

3,900

$

22,000

March

2,900

$

14,000

April

4,100

$

24,000

May

4,800

$

28,750

June

4,300

$

23,000

July

5,500

$

25,250

August

4,500

$

23,250

September

3,000

$

16,500

October

4,700

$

27,000

November

6,800

$

32,000

December

6,000

$

28,250

  

Summary Output

Regression Statistics

Multiple R

.919

R Square

.844

Adjusted R2

.829

Standard Error

2,165.73

Observations

12.00

Coefficients

Standard Error

t Stat

P-value

Lower 95%

Upper 95%

Intercept

5,084.31

2,589.60

1.96

0.08

(685.68)

10,854.29

Machine Hours

4.11

0.56

7.36

0.00

2.86

5.35


If the controller uses high-low method to estimate costs, the cost equation for electricity cost is:( Round intermediate calculations to 2 decimal places)

Multiple choice:

  1. Electricity costs= $21.716
  2. Electricity costs= $5,084.31 + ($4.11 * machine-hours)
  3. Electricity cost = $584 + (4.62 * machine-hours)
  4. Electricity costs = $5.40 * Machine-hours

Homework Answers

Answer #1

Highest electricity cost is $ 32000 in the month of november for which machine hours given is 6800.

Lowest electricity cost is $ 14000 in the month of march for which machine hours given is 2900.

The cost equation for electricity cost is :-

variable cost portion calculation :-

( 32000 - 14000 ) / ( 6800 - 2900 ) =

18000 / 3900 = $ 4.62 * machine hours

fixed cost portion calculation :-

32000 - [ 6800 * 4.62 ] = $ 584

The cost equation for electricity cost is :-$584 + (4.62 * machine-hours)

Option C is correct.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Research into the relationship between hours of study and grades show widely different conclusions. A recent...
Research into the relationship between hours of study and grades show widely different conclusions. A recent survey of graduates who wrote the Graduate Management Admissions Test (GMAT) had the following results. Hours Studied Average Score (Midpoint) 64 350 72 450 79 550 106 650 99 750 The Excel output for this regression is as following SUMMART OUTPUT ____________________________    Regression Statistics ____________________________ Multiple R 0.919958 R Square 0.846322 Adjusted R Square 0.795097 Standard Error 71.57225 Observations 5 Anova ___________________________________________________________________________________________   ...
Item14 Item14 Item 14 Burmer Co. has accumulated data to use in preparing its annual profit...
Item14 Item14 Item 14 Burmer Co. has accumulated data to use in preparing its annual profit plan for the upcoming year. The cost behavior pattern of the maintenance costs must be determined. Data regarding the machine hours and maintenance costs for the last year and the results of the regression analysis are as follows: Month Maintenance Cost Machine Hours Jan. $ 5,040 620 Feb. 3,600 420 Mar. 4,320 520 Apr. 3,380 390 May 5,220 650 June 3,550 400 July 3,640...
Burmer Co. has accumulated data to use in preparing its annual profit plan for the upcoming...
Burmer Co. has accumulated data to use in preparing its annual profit plan for the upcoming year. The cost behavior pattern of the maintenance costs must be determined. Data regarding the machine hours and maintenance costs for the last year and the results of the regression analysis are as follows: Month Maintenance Cost Machine Hours Jan. $ 5,040 620 Feb. 3,600 420 Mar. 4,320 520 Apr. 3,380 390 May 5,220 650 June 3,550 400 July 3,640 430 Aug. 5,360 680...
Burmer Co. has accumulated data to use in preparing its annual profit plan for the upcoming...
Burmer Co. has accumulated data to use in preparing its annual profit plan for the upcoming year. The cost behavior pattern of the maintenance costs must be determined. Data regarding the machine hours and maintenance costs for the last year and the results of the regression analysis are as follows: Month Maintenance Cost Machine Hours Jan. $ 5,040 620 Feb. 3,600 420 Mar. 4,320 520 Apr. 3,380 390 May 5,220 650 June 3,550 400 July 3,640 430 Aug. 5,360 680...
Month Machine Hours (hrs.) Maintenance Costs ($) 1 1,330 102,694 2 1,400 103,694 3 1,500 108,694...
Month Machine Hours (hrs.) Maintenance Costs ($) 1 1,330 102,694 2 1,400 103,694 3 1,500 108,694 4 1,470 108,694 5 1,620 116,694 6 1,690 115,694 7 1,490 107,694 8 1,310 102,694 9 1,450 106,694 10 1,580 113,694 11 1,300 100,694 12 1,600 113,694 13 1,650 114,694 14 1,440 109,694 15 1,340 102,694 16 1,670 114,694 17 1,480 106,694 18 1,360 103,694 19 1,340 103,694 20 1,540 112,694 Assume that the following relationship holds: Maintenance Costs = (v * Machine Hours)...
1) If a machine in a manufacturing process is not working correctly, company policy dictates that...
1) If a machine in a manufacturing process is not working correctly, company policy dictates that the machine must be stopped and serviced. Ho: Machine is working correctly   HA: Machine is not working correctly One day, the machine was left working but in fact it should have been stopped for a service. What type of error would this be? Select one: A) Type I B) No error has been made. C) Type II error D) Type I and Type II...
Armer Company is accumulating data to use in preparing its annual profit plan for the coming...
Armer Company is accumulating data to use in preparing its annual profit plan for the coming year. The cost behavior pattern of the maintenance costs must be determined. The accounting staff has suggested the use of linear regression to derive an equation for maintenance hours and costs. Data regarding the maintenance hours and costs for the last year and the results of the regression analysis follow: Month Maintenance Cost Machine Hours Jan. $ 4,950 780 Feb. 3,750 620 Mar. 4,350...
Armer Company is accumulating data to use in preparing its annual profit plan for the coming...
Armer Company is accumulating data to use in preparing its annual profit plan for the coming year. The cost behavior pattern of the maintenance costs must be determined. The accounting staff has suggested the use of linear regression to derive an equation for maintenance hours and costs. Data regarding the maintenance hours and costs for the last year and the results of the regression analysis follow: Month Maintenance Cost Machine Hours Jan. $ 4,200 480 Feb. 3,000 320 Mar. 3,600...