tom has the following information for the last 4 months
month. units. total costs
sept.
7,000. $100,300
oct.
8,000. $100,700
nov.
6,000. $105,700
dec.
7,500. $103,200
using the high/low method, estimate total cost at
7,700 units
estimated total costs_______
Under high-low point method,
(a)
Variable cost per unit = (highest activity cost - lowest activity
cost)/(highest activity units - lowest activity units)
= ($100700 - $105700)/(8000 - 6000)
= -$2.5 per machine hour
(It is a negative variable cost per unit)
(b)
to get the total fixed cost, let's take e.g. data for November
Total fixed cost = total cost - (units produced x variable cost
per unit)
= $105700 - {6000 x (-$2.5)}
= $120700
(c)
therefore, for 7700 units:
estimated total costs = total fixed costs + total variable costs
= $120700 + {7700 x (-$2.5)}
= $101450