We are building a simple storage facility for covered storage of bulk raw materials. | |||||||||||||
The Budget is as Follows: | |||||||||||||
The concrete floor is budgeted at $5000. The walls and doors are budgeted at $9000. The roof is budgeted at $5000. | |||||||||||||
The plan is as follows: | |||||||||||||
The floor will require 2 days to complete, the walls and doors will require 4 days to complete, and the roof will require 2 days to complete. | |||||||||||||
Actual work Complete to Date is as follows: | |||||||||||||
The floor required 3 days to complete and it costs $5600. Due to material shipping delays, the walls and doors took 5 days to complete, but were on budget. | |||||||||||||
We have been working 1 day on the roof, and have spent $3000 so far. We are about halfway done with the roof. | |||||||||||||
We are at the end of day 9, and we need to provide project status. | |||||||||||||
Calculate the CPI, SPI, ETC, and EAC for our project. Remember to show all work and state assumptions. | |||||||||||||