Barley Hopp, Inc., manufactures custom-ordered commemorative
beer steins. Its standard cost information follows:
Standard Quantity | Standard Price (Rate) | Standard Unit Cost | ||||||
Direct materials (clay) | 1.70 | lbs. | $ | 1.80 | per lb. | $ | 3.06 | |
Direct labor | 1.70 | hrs. | $ | 10.00 | per hr. | 17.00 | ||
Variable manufacturing overhead (based on direct labor hours) | 1.70 | hrs. | $ | 1.40 | per hr. | 2.38 | ||
Fixed manufacturing overhead ($346,500.00 ÷ 165,000.00 units) | 2.10 | |||||||
Barley Hopp had the following actual results last year:
Number of units produced and sold | 170,000 | |
Number of pounds of clay used | 308,200 | |
Cost of clay | $ | 585,580 |
Number of labor hours worked | 215,000 | |
Direct labor cost | $ | 2,795,000 |
Variable overhead cost | $ | 330,000 |
Fixed overhead cost | $ | 340,000 |
Required:
1. Calculate the direct materials price, quantity, and
total spending variances for Barley Hopp. (Do not round
your intermediate calculations. Indicate the effect of each
variance by selecting "F" for favorable and "U" for
unfavorable.)
direct materials price variance
direct materials quantity variance
direct materials spending variance
2. Calculate the direct labor rate, efficiency,
and total spending variances for Barley Hopp.
(Do not round your intermediate calculations. Indicate the
effect of each variance by selecting "F" for favorable and "U" for
unfavorable.)
Direct Labor
Efficiency
Total spending variances
3. Calculate the variable overhead rate,
efficiency, and total spending variances for Barley
Hopp. (Do not round your intermediate
calculations. Indicate the effect of each variance by selecting "F"
for favorable/Overapplied and "U" for
unfavorable/underapplied.)
overhead rate variance
efficiency variance
spending variances
1) Direct material price variance = (SP-AP) AQ = (1.8*308200-585580) = 30820 U
Direct material quantity variance = (SQ-AQ)SP = (170000*1.7-308200)*1.8 = 34560 U
Total material variance = (170000*3.06-585580) = 65380 U
2) Direct labor rate variance = (SR-AR)AH = (10*215000-2795000) = 645000 U
Direct labor efficiency variance = (SH-AH)SR = (170000*1.7-215000)*10 = 740000 F
Total labor variance = (170000*17-2795000) = 95000 F
3) Variable overhead rate variance = (1.4*215000-330000) = 29000 U
Variable overhead efficiency variance = (289000-215000)*1.4 = 103600 F
Total Variable overhead variance = (170000*2.38-330000) = 74600 F