Estimated factory overhead cost for fiscal year beginning August 1 $795,210 $961,000 Estimated direct labor hours...

Estimated factory overhead cost for fiscal
year beginning August 1 $795,210 $961,000
Estimated direct labor hours for year 15,500
Estimated machine hours for year 20,390
Actual factory overhead costs for August $63,560 $83,330
Actual direct labor hours for August 1,400
Actual machine hours for August 1,590

a. Determine the factory overhead rate for Factory 1.
$ per machine hour

b. Determine the factory overhead rate for Factory 2.
$ per direct labor hour

c. Journalize the entries to apply factory overhead to production in each factory for August. If an amount box does not require an entry, leave it blank.

Factory 1
Factory 2

d. Determine the balances of the factory overhead accounts for each factory as of August 31, and indicate whether the amounts represent overapplied factory overhead or underapplied factory overhead.

Factory 1 $
Factory 2 $

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies...
Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning August 1 $556,660 $768,800 Estimated direct labor hours for year 12,400 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies...
Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning August 1 $675,000 $735,300 Estimated direct labor hours for year 12,900 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies...
Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning August 1 $18,500,000 $44,000,000 Estimated direct labor hours for year 800,000 Estimated machine hours for...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $580,500 $540,000 Estimated direct labor hours for year 9,000 Estimated machine hours for year 23,220 Actual factory overhead costs for...
Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies...
Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning August 1 $810,550 $672,800 Estimated direct labor hours for year 11,600 Estimated machine hours for...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $498,200 $768,000 Estimated direct labor hours for year 12,000 Estimated machine hours for year 24,910 Actual factory overhead costs for...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $685,980 $672,000 Estimated direct labor hours for year 10,500 Estimated machine hours for year 18,540 Actual factory overhead costs for...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $676,900 $676,500 Estimated direct labor hours for year 12,300 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $665,260 $1,020,000 Estimated direct labor hours for year 15,000 Estimated machine hours for...
ackson Inc. listed the following data for 2016: Budgeted factory overhead $1,271,000 Budgeted direct labor hours...
ackson Inc. listed the following data for 2016: Budgeted factory overhead $1,271,000 Budgeted direct labor hours 82,000 Budgeted machine hours 41,000 Actual factory overhead 1,201,000 Actual direct labor hours 86,300 Actual machine hours 39,400 Round calculations to 2 significant digits If overhead is applied based on direct labor hours, overapplied/underapplied overhead is: $136,650 overapplied. $136,650 underapplied. $174,775 underapplied. $174,775 overapplied. $-0-. Sutherland Company listed the following data for 2016: Budgeted factory overhead $2,100,000 Budgeted direct labor hours 89,000 Budgeted machine...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT