Question

Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two...

Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,650, and Job 94 with a beginning balance of $7,270. Jagjit applies overhead at the rate of $9 per direct labor hour. Direct labor wages average $16 per hour. Data on August costs for all jobs are as follows:

Job 93 Job 94 Job 95 Job 96
Direct materials $910 $4,590 $3,330 $1,270
Direct labor cost 2,080 4,800 2,400 960

During August, Jobs 95 and 96 were started. Job 93 was completed on August 17, and the client was billed at cost plus 40%. All other jobs remained in process.

Refer to the list below for the exact wording of text items within your job-order cost sheets.

Amount Descriptions
Applied overhead
Beginning balance
Direct labor
Direct materials

Total

Jagjit Company

Job-Order Cost Sheets

August 31

1

Job 93

Job 94

Job 95

Job 96

2

Beginning balance

3

4

5

6

4. Calculate the balance in Work in Process on August 31.

The work in process balance on August 31 is .

Points:

0 / 1

5. What is the price of Job 93?

The price of Job 93 is .

Points:

0 / 1

Partway through the year, Jagjit bought a bulldozer to handle larger jobs. The bulldozer cost $38,500 and is needed for larger commercial jobs. Smaller residential jobs can still be done with the smaller bobcat tractor.

6. CONCEPTUAL CONNECTION: Complete the statement below that outlines how the bulldozer’s cost could be applied to only those jobs that need the larger equipment.

Create a separate ________   for the acquisition and use of the bulldozer. Treat the bulldozer’s depreciation, fuel, maintenance, etc. as _______ . Divide this by the anticipated annual hours of use to arrive at the ___________ .

Homework Answers

Answer #1

Hi

Let me know in case you face any issue:

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers....
Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,700 and Job 94 with a beginning balance of $7,200. Jagjit applies overhead at the rate of $6 per direct labor hour. Direct labor wages average $18 per hour. Data on August costs for all jobs are as follows: Job 93 Job 94 Job 95 Job 96 Direct...
Sheds, Inc. designs and builds sheds and outbuildings for individual customers. The company uses a job...
Sheds, Inc. designs and builds sheds and outbuildings for individual customers. The company uses a job cost system and treats each customer's order as a separate job. At the beginning of January the company had the following raw material inventory: $600 At the beginning of January the company had the following work-in-process inventories: Job 21 $13,000 Job 25 $9,000 During January, the following activities took place: 1. Started jobs 26 and 27. 2. Purchased raw materials in January: $12,000 Requisitioned...
At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is...
At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 400 units for Job 40 at $10 per unit and 1,500 units for Job 42 at $14 per unit. During August, Prichard Company accumulated 400 hours of direct labor costs on Job 40 and 1,200...
At the end of August, Darling Company had completed Jobs 40 and 42. Job 40 is...
At the end of August, Darling Company had completed Jobs 40 and 42. Job 40 is for 500 units, and Job 42 is for 200 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 300 units for Job 40 at $18 per unit and 900 units for Job 42 at $20 per unit. During August, Darling Company accumulated 600 hours of direct labor costs on Job 40 and 1,100...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 2,000 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 300 units for Job 40 at $16 per unit and 1,000 units for Job 42 at $24 per unit. During August, Prichard Company accumulated 600 hours of direct labor costs on Job 40...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
enkins Company uses a job order cost system with overhead applied to jobs on the basis...
enkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Job Costs At the end of August, Kaye Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Kaye Company had completed Jobs 40 and 42. Job 40 is for 1,000 units, and Job 42 is for 200 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 200 units for Job 40 at $20 per unit and 1,400 units for Job 42 at $16 per unit. During August, Kaye Company accumulated 300 hours of direct labor costs on Job 40...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of March, Mendez Company had two jobs in process, Job 86 and Job 87, with the following accumulated cost information: Job 86 Job 87 Direct materials $4,800 $1,600 Direct labor 1,200 3,000 Applied overhead 888 2,220 Balance, March 1 $6,888 $6,820 During March, two more jobs (88 and 89) were started. The following direct materials and direct labor costs were added to...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT