Question

If a firm underestimated the risk, that is the opportunity cost of two mutually exclusive projects...

If a firm underestimated the risk, that is the opportunity cost of two mutually exclusive projects

One variable at a time related to the project are randomly, repeatedly modified using a computer program to develop a very wide range of NPVs, which can then be averaged to give an idea of the expected outcome best describes

Historically, which financial asset has exhibited the most risk for an investor?

Homework Answers

Answer #1

A financial asset is an asset whose value is derived from a contractual claim, such as bank deposits, bonds, and stocks. Financial assets are more liquid than other assets, such as commodities or real estate, and may be traded on financial markets.

Equity shares in particular are more risky form of financial asset for an investor. Shares represent ownership percentage in the company. Performance of these financial assets depend majorly upon how well the company performs . However with high risk comes chances of high reward thats what makes these investment such an attractive option. The return on the equity may be in the form of capital appriciation or in the form of dividend.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The NPV profile of two mutually exclusive projects can be useful in identifying: the interest rates...
The NPV profile of two mutually exclusive projects can be useful in identifying: the interest rates in which an investor would prefer one to the other, the profile would also indicate a possible interest rate in which an investor is indifferent between the alternatives. the optimal payback period of the projects given the investors criteria the interest rate that the investor should choose to evaluate the projects All of the above answers are correct.
Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost...
Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost of capital; answer the next 2 questions: year Project A Project B 0 -5000 -1000 1 2500 600 2 2500 600 3 2500 600 1)  Which project should be accepted, if any and why? A: Project B; it has a higher IRR and PI B: Neither project should be accepted, they both have negative NPVs C: Both project should be accepted; they have IRRs greater...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial Investment (CF0) $12,900 $12,900 Outcome Annual cash inflows (CF) Pessimistic $860 1500 Most likely 1690 1690 Optimistic 2480 1740 a. Determine the range of annual cash inflows...
Two projects being considered by a firm are mutually exclusive and have the following projected cash...
Two projects being considered by a firm are mutually exclusive and have the following projected cash flows:      Year                               Project A                       Project B                                             Cash Flow                     Cash flow        0                                      (2000)                            (2000)        1                                         0                                     832        2                                         0                                     832        3                                         0                                     832        4                                       3877                                 832                                  Based only on the information given, which of the projects would be preferred and why? Mark the correct answer but justify your answer showing your computations. a.Project A, because it has...
You are considering two mutually exclusive projects. Based upon risk, the appropriate discount rate for both...
You are considering two mutually exclusive projects. Based upon risk, the appropriate discount rate for both projects is 10%. The first project has an IRR of 22% and an NPV of $22,432. The second project has an IRR of 12% and an NPV of $24,456. Which project should you select? accept both projects since both are acceptable. pick the project with the shorter payback period. choose the project with the higher NPV. unable to determine due to insufficient information. choose...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 8 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and three years, respectively. Time 0 1 2 3 Project A Cashflow -20,000 10,000 30,000 1,000 Project B Cashflow -30,000 10,000 20,000 50,000 Calculate the NPV and use the NPV decision rule to...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 12 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -29,000 19,000 39,000 10,000   Project B Cash Flow -39,000 19,000 29,000 59,000 Use the PI decision rule to evaluate these...
19. Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
19. Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 10 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -32,000 22,000 42,000 13,000   Project B Cash Flow -42,000 22,000 8,000 62,000 Use the payback decision rule to evaluate...
You are trying to determine which of two mutually exclusive projects to undertake. Both projects have...
You are trying to determine which of two mutually exclusive projects to undertake. Both projects have the same initial outlay. Project Adam has an NPV of $4,392.15, an IRR of 11.33%, and an EAA of $1,158.64. Project Eve has an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1,093.50. The cost of capital for both projects is 9%, the projects have different lives, and the projects are not repeatable. What should you do? You should do Project...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 10 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and a half and three and a half years, respectively. Time 0 1 2 3 Project A Cash Flow ?1,000 300 400 700 Project B Cash Flow ?500 200 400 300 Use...