Entry for Jobs Completed; Cost of Unfinished Jobs
The following account appears in the ledger prior to recognizing the jobs completed in August:
Work in Process | ||
Balance, August 1 | $17,850 | |
Direct materials | 145,120 | |
Direct labor | 156,540 | |
Factory overhead | 82,290 |
Jobs finished during August are summarized as follows:
Job 210 | $72,320 |
Job 216 | 44,200 |
Job 224 | 84,380 |
Job 230 | 156,700 |
a. Journalize the entry to record the jobs completed.
fill in the blank 21f1d806cff002a_2 | |||
fill in the blank 21f1d806cff002a_4 |
b. Determine the cost of the unfinished jobs at
August 31.
$fill in the blank 92d95afdbfe1f80_1
Solution
Calculation of amount of total jobs completed: | Amount $ | |
Job 210 | 72,320 | |
Job 224 | 84,380 | |
Job 216 | 44,200 | |
Job 230 | 156,700 | |
Cost of completed jobs | 357,600 | |
Answer a | ||
Journal Entry | ||
Account | Debit $ | Credit $ |
Finished Goods | 357,600 | |
Work In Process | 357,600 | |
Calculation of work in process | Amount $ | |
Balance at August 1 | 17,850 | |
Direct Materials | 145,120 | |
Direct Labor | 156,540 | |
Factory Overhead | 82,290 | |
Balance in work in process | 401,800 | |
Answer b | Amount $ | |
Balance in work in process | 401,800 | |
Less: Cost of completed jobs | 357,600 | |
Cost of unfinished jobs on August 31 | 44,200 |