Question

Prince Company’s total overhead costs at various levels of activity are presented below:   Month Machine Hours...

Prince Company’s total overhead costs at various levels of activity are presented below:
  Month Machine Hours Total
Overhead
Cost
  September 112,800 $ 781,512
  October 89,200 $ 662,568
  November 157,200 $ 1,005,288
  December 165,000 $ 1,044,600

Assume that the overhead cost above consists of utilities, supervisory salaries, depreciation, and maintenance. The breakdown of these costs at the 89,200-machine-hour level of activity in October is as follows:

  Utilities (variable) $ 233,704
  Supervisory salaries
      and depreciation (fixed)
172,000
  Maintenance (mixed)      256,864
  Total overhead cost $ 662,568

  

The company wants to break down the maintenance cost into its variable and fixed cost elements.
Required:
1.

Estimate how much of the $1,044,600 of overhead cost in December was maintenance cost. (Hint: To do this, first determine how much of the $1,044,600 consisted of utilities and supervisory salaries. Think about the behaviour of variable and fixed costs within the relevant range.) (Do not round intermediate calculations.)

      

2.

Using the high–low method, estimate a cost formula for maintenance. (Round variable cost to 2 decimal places and fixed cost to the nearest dollar amount.)

      

3.

Express the company’s total overhead cost in the form Y = a + bX. (Round variable cost to 2 decimal places and fixed cost to the nearest dollar amount.)

      

4.

What total overhead cost would you expect to be incurred at an activity level of 99,200 machine-hours? (Do not round intermediate calculations.)

      

Homework Answers

Answer #1

1. Estimate how much of the $1,044,600 of overhead cost in December was maintenance cost.

Utilities (variable) (2.62*165000) 432300
Supervisory salaries
      and depreciation (fixed)
172000
Maintenance (mixed) 440300
Total overhead cost 1044600

2. Using the high–low method, estimate a cost formula for maintenance

Variable cost per machine hour = Change in cost/change in machine hour

= 440300-256864/165000-89200

Variable cost per machine hour = 2.42 per machine hour

Fixed cost = Total cost-variable cost

= 440300-165000*2.42

Fixed cost = 41000

3. Express the company’s total overhead cost in the form Y = a + bX.

Y= a+bx

Y = 41000+2.42X

4. Total overhead cost on 99200 machine hour :

Total overhead cost = (99200*2.42)+41000 = 281064

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 49,000    $173,870        May 39,000    $151,570        June 59,000    $196,170        July 69,000    $218,470   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 42,900     Supervisory salaries (fixed) 46,000   Maintenance (mixed) 62,670   Total overhead cost $ 151,570 The...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 198,260 May 42,000 $ 172,460 June 62,000 $ 224,060 July 72,000 $ 249,860 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 58,800 Supervisory salaries (fixed) 49,000 Maintenance (mixed) 64,660 Total overhead cost $ 172,460 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 48,000 $ 217,820 May 38,000 $ 190,420 June 58,000 $ 245,220 July 68,000 $ 272,620 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 38,000 machine-hour level of activity is: Utilities (variable) $ 57,000 Supervisory salaries (fixed) 70,000 Maintenance (mixed) 63,420 Total overhead cost $ 190,420 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 48,000 $ 199,940 May 38,000 $ 172,640 June 58,000 $ 227,240 July 68,000 $ 254,540 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 38,000 machine-hour level of activity is: Utilities (variable) $ 57,000 Supervisory salaries (fixed) 54,000 Maintenance (mixed) 61,640 Total overhead cost $ 172,640 Nova Company’s...
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of...
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 51,000 $ 181,360 May 41,000 $ 157,760 June 61,000 $ 204,960 July 71,000 $ 228,560 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) $ 53,300 Supervisory salaries (fixed) 48,000 Maintenance (mixed) 56,460...
Neevey Inc. tracks activity based on machine-hours. In March, Neevy used 3000 machine-hours. Manufacturing overhead costs...
Neevey Inc. tracks activity based on machine-hours. In March, Neevy used 3000 machine-hours. Manufacturing overhead costs were incurred as follows: $18000.....Utilities (a variable cost) $35300.....Maintenance (a mixed cost) $21000......Supervisor salaries (a fixed cost) $74300....Total overhead in March Total overhead in April was $87050 and machine-hours in April was 4500. Do not enter expenses as negative numbers. 1. How much of the April overhead must have been for Utilities? 2. How much of the April overhead must have been for Maintenance?
Neevey Inc. tracks activity based on machine-hours. In March, Neevy used 2900 machine-hours. Manufacturing overhead costs...
Neevey Inc. tracks activity based on machine-hours. In March, Neevy used 2900 machine-hours. Manufacturing overhead costs were incurred as follows: $14500.....Utilities (a variable cost) $35050..... Maintenance (a mixed cost) $18000...... Supervisor salaries (a fixed cost) $67550.... Total overhead in March Total overhead in April was $89400 and machine-hours in April was 5200. Do not enter expenses as negative numbers. 1. How much of the April overhead must have been for Utilities? 2. How much of the April overhead must have...
Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 3,800 machine-hours...
Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 3,800 machine-hours Variable overhead costs: Supplies $ 22,040 Indirect labor 36,860 Fixed overhead costs: Supervision 16,900 Utilities 7,200 Depreciation 8,200 Total overhead cost $ 91,200 The company's variable overhead costs are driven by machine-hours. What would be the total budgeted overhead cost for next month if the activity level is 3,700 machine-hours rather than 3,800 machine-hours?
1. X Company uses account analysis to estimate total overhead costs for each month, with units...
1. X Company uses account analysis to estimate total overhead costs for each month, with units produced as the activity measure. In May, when production was 1,000 units, the plant manager classified each overhead cost item as fixed and variable as follows: Cost Item Total Cost Cost Behavior Utilities    $21,200   100% variable Supplies     23,100 60% variable Maintenance     20,000 100% fixed If September production is expected to be 1,180 units, what are estimated total overhead costs in September (round unit costs...
WWW Company’s flexible budget for manufacturing overhead follows: Account Machine Hours Machine Hours Machine Hours 8,000...
WWW Company’s flexible budget for manufacturing overhead follows: Account Machine Hours Machine Hours Machine Hours 8,000 9,000 10,000 Variable Overhead $10,000 $11,250 $12,500 Fixed Overhead $28,000 $28,000 $28,000 Total Overhead Costs $38,000 $39,250 $40,500             The following additional information is available for the most recent period: The activity level of 8,000 machine hours was chosen to compute the predetermined overhead rate At 8,000 machine hours level of activity the company should produce 3,200 units of output The company’s actual operating...