1. Labor Mix Variance = (Actual Hours Used at Standard Mix) – (Actual Hours used at Actual Mix) * Standard Hourly Price
Labor Mix Variance for the given values
Engineering |
Carpentry |
Masonry |
(500 – 550) * 8 |
(500 – 650) * 7 |
(500- 375) *5 |
-50 * 8 |
-150* 7 |
125 * 5 |
-400 |
-1050 |
625 |
2. Labor Yield Variance = (Actual Hours used at Actual Mix) - (Actual Hours Used at Standard Mix) * Standard Hourly Price
Labor Yield Variance for the given values
Engineering |
Carpentry |
Masonry |
(550-500) * 8 |
(650-500) * 7 |
(375-500) *5 |
50 * 8 |
150* 7 |
-125 * 5 |
400 |
1050 |
-625 |