Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect to Jobs A and B:
Estimated Data | Machining | Assembly | Total | ||||||
Manufacturing overhead | $ | 7,056,000 | $ | 441,000 | $ | 7,497,000 | |||
Direct labor-hours | 21,000 | 336,000 | 357,000 | ||||||
Machine-hours | 336,000 | 16,000 | 352,000 | ||||||
Job A | Machining | Assembly | Total |
Direct labor-hours | 5 | 10 | 15 |
Machine-hours | 11 | 2 | 13 |
Job B | Machining | Assembly | Total |
Direct labor-hours | 4 | 5 | 9 |
Machine-hours | 12 | 3 | 15 |
Required:
1.A.) If Mason Company uses a plantwide predetermined overhead rate with direct labor-hours as the allocation base, how much manufacturing overhead cost would be applied to Job A? Job B?
1.B.) Assume that Mason Company uses departmental predetermined
overhead rates. The Machining Department is allocated based on
machine-hours and the Assembly Department is allocated based on
direct labor-hours. How much manufacturing overhead cost would be
applied to Job A? Job B? (Round your intermediate
calculations and final answers to 2 decimal places.)
Get Answers For Free
Most questions answered within 1 hours.