Elite, Inc. has estimated total factory overhead costs of $900,000, and 25,000 direct labor hours for the current fiscal year. If the direct labor hours for Job N41 is 2,000, calculate the total factory overhead applied to this job.
a.$4,000
b.$72,000
c.$40,000
d.$25,000
Ans. | Option b $72,000 | ||
*First of all, we need to calculate the predetermined overhead rate. | |||
Predetermined overhead rate = Estimated factory overhead cost / Estimated direct labor hours | |||
$900,000 / 25,000 | |||
$36 per direct labor hour | |||
*Now we can calculate the applied overhead amount by the following way: | |||
Overhead applied = Actual direct labor hours * Predetermined overhead rate | |||
2,000 * $36 | |||
$72,000 | |||