Question

The following information is available for Department C for the month of August: Units Cost Work...

The following information is available for Department C for the month of August:

Units Cost
Work in process, August 1 (70% complete) 10,000
Direct materials $36,000
Direct labor 18,000
Manufacturing overhead 24,000
Total work in process, August 1 $78,000
Started in production during August 40,000
Costs added:
Direct materials $108,000
Direct labor 48,000
Manufacturing overhead 61,040
Total costs added during August $217,040
Work in process, August 31 (80% complete)   4,000
Units completed and transferred out 42,000


Materials are added at the beginning of the process. Inspection takes place at the 50 percent point in the conversion process to determine spoiled units. Round unit costs to two decimal places. The company uses the weighted average cost flow assumption.

Department C's equivalent units of production for conversion using the weighted average method is

a.54,000.

b.50,000.

c.44,800.

d.47,200.

Homework Answers

Answer #1

Equivalent unit of production for conversion = Unit transferred out+Equivalent unit of spoiled unit+Equivalent unit of EWIP

                                                               = 42000+(4000*50%)+(4000*80%)

Equivalent unit of production for conversion = 47200

So answer is d) 47200

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Badgersize Company has the following information for its Forming Department for the month of August. Work...
Badgersize Company has the following information for its Forming Department for the month of August. Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete $ 80,000 Conversion: 20% complete 24,000 Balance in work in process, August 1 $ 104,000 Units started during August 48,000 Units completed and transferred in August 59,000 Work in process (70% complete), August 31 ? Costs charged to Work in Process in August Direct materials $ 141,000 Conversion costs: Direct labor $ 107,000...
Production information shows the following costs and units for the smoothing department in August. Cost Units...
Production information shows the following costs and units for the smoothing department in August. Cost Units Work in process Beginning balance: materials $1,450 Beginning units 630 Beginning balance: conversion 2,700 Transferred in 1,770 Materials 7,190 Transferred out 1,780 Labor 14,500 Overhead 7,552 All materials are added at the beginning of the period. The ending work in process is 20% complete as to conversion. What is the value of the inventory transferred to finished goods and the value of the WIP...
Refer to the following information about the Finishing Department in the Davidson Factory for the month...
Refer to the following information about the Finishing Department in the Davidson Factory for the month of June. Davids on Factory uses the weighted -average method of inventory costing. Beginning Work in Process inventory: Physical units ....................................................................... 5,000 units % complete for materials ..................................................... 70% % complete for labor and overhead ..................................... 25% Materials co st from May ...................................................... $7,350 Labor and overhead cost from May ...................................... $3,125 Product started and completed: Physical units ....................................................................... 40,000 units Ending Work in...
The debits to Work in Process—Roasting Department for Morning Brew Coffee Company for August, together with...
The debits to Work in Process—Roasting Department for Morning Brew Coffee Company for August, together with information concerning production, are as follows: Work in process, August 1, 500 pounds, 40% completed $2,370* *Direct materials (500 X $4.1) $2,050 Conversion (500 X 40% X $1.6) $320 $2,370 Coffee beans added during August, 16,000 pounds 64,800 Conversion costs during August 26,758 Work in process, August 31, 800 pounds, 30% completed ? Goods finished during August, 15,700 pounds ? All direct materials are...
Department A had no Work-in-Process at the beginning of the period, 1,900 units were completed during...
Department A had no Work-in-Process at the beginning of the period, 1,900 units were completed during the period, 650 units were 50% completed at the end of the period, and the following manufacturing costs were debited to the departmental Work-in-Process account during the period   Direct materials (2,550 at $19.00) $ 48,450     Direct labor 24,030     Factory overhead 16,020   Assuming that all direct materials are added at the beginning of production and Department A uses weighted-average process costing, what is the total...
Sheridan Company has gathered the following information. Units in beginning work in process 20,900 Units started...
Sheridan Company has gathered the following information. Units in beginning work in process 20,900 Units started into production 249,100 Units in ending work in process 26,100 Percent complete in ending work in process:     Conversion costs 60 %     Materials 100 % Costs incurred:     Direct materials $108,000     Direct labor $580,202     Overhead $185,500 Compute equivalent units of production for materials and for conversion costs. Materials Conversion Costs The equivalent units of production    Determine the unit costs of production. (Round unit costs to...
In the month of September, a department had 20,000 units in beginning work in process that...
In the month of September, a department had 20,000 units in beginning work in process that were 50% complete. During September, 100,000 units were transferred into production from another department. At the end of September there were 10,000 units in ending work in process that were 60% complete. Materials are added at the beginning of the process, while conversion costs are incurred uniformly throughout the process. How many units were transferred out of the process in September? In the month...
The Mercer Corporation prepared the following production cost report for Department 1 for October of the...
The Mercer Corporation prepared the following production cost report for Department 1 for October of the current year. Physical Units Work in process inventory, October 1 0 units Units started in production in October 7,800 units Units transferred to finished goods inventory during October 7,000 units Costs incurred in December: Direct materials                                               $24,192 Direct labor and manufacturing overhead      $53,070 Work in process inventory on October 31 is 70% complete as to direct materials and 40% complete as to conversion costs....
Please show work: Bixby Carpet Manufacturing Inc. uses a process costing system and calculates per-unit costs...
Please show work: Bixby Carpet Manufacturing Inc. uses a process costing system and calculates per-unit costs using the weighted average method. The following data relates to the first production department (the Weaving Department) of its Rayon carpet brand for the month of November. Beginning Work in Process Inventory: 900 units, 40% complete Ending Work in Process Inventory: 1,200 units, 50% complete Units started: 15,600 units All direct materials are added at the beginning of the process, and conversion costs are...
The Mixing Department of Cherry Manufacturing Company has the following production and manufacturing cost data for...
The Mixing Department of Cherry Manufacturing Company has the following production and manufacturing cost data for January. Production: Beginning inventory 8,000 units that are 100% complete as to materials and 40% complete as to conversion costs; units started into production 27,000; ending inventory of 12,000 units 20% complete as to conversion costs. Manufacturing Costs: Beginning work in process inventory of $40,000, comprised of $30,000 of materials and $10,000 of conversion costs. Materials added during the month, $110,000; labor and overhead...