The following information is available for Department C for the
month of August:
Units | Cost | ||
Work in process, August 1 (70% complete) | 10,000 | ||
Direct materials | $36,000 | ||
Direct labor | 18,000 | ||
Manufacturing overhead | 24,000 | ||
Total work in process, August 1 | $78,000 | ||
Started in production during August | 40,000 | ||
Costs added: | |||
Direct materials | $108,000 | ||
Direct labor | 48,000 | ||
Manufacturing overhead | 61,040 | ||
Total costs added during August | $217,040 | ||
Work in process, August 31 (80% complete) | 4,000 | ||
Units completed and transferred out | 42,000 |
Materials are added at the beginning of the process. Inspection
takes place at the 50 percent point in the conversion process to
determine spoiled units. Round unit costs to two decimal places.
The company uses the weighted average cost flow assumption.
Department C's equivalent units of production for conversion using
the weighted average method is
a.54,000.
b.50,000.
c.44,800.
d.47,200.
Equivalent unit of production for conversion = Unit transferred out+Equivalent unit of spoiled unit+Equivalent unit of EWIP
= 42000+(4000*50%)+(4000*80%)
Equivalent unit of production for conversion = 47200
So answer is d) 47200
Get Answers For Free
Most questions answered within 1 hours.