The total variance is $9700 favourable. The total materials variance is $4300 favourable. The total labour variance is twice the total overhead variance, both which are favourable. What is the total overhead variance?
|
|||
|
|||
|
|||
|
The correct answer is "$1,800". |
Calculation: |
Data Given in the Question: |
Direct Labour variance = 2*Overhead Variance |
Materials Variance = $4,300 favourable |
Total Variance = $9,700 favourable |
Now, let overhead variance be "X". |
Hence, Direct Labour variance = 2X |
Total Variance = Materials Variance + Labour Variance + Overheads Variance |
$9,700 = $4,300 + 2X + X |
3X = $5,400 |
X = $1,800 |
Therefore, Overheads Variance = $1,800 favourable |