Question

Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On...

Applying Overhead to Jobs, Costing Jobs

Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18,710 to date.

During October, Jobs 878, 879, and 880 were started. Data on costs added during October for all jobs are as follows:

Job 877 Job 878 Job 879 Job 880
Direct materials $14,380 $5,960 $3,550 $1,790
Direct labor 14,600 8,200 1,700 1,900

Overhead is applied to production at the rate of 80% of direct labor cost. Job 877 was completed on October 28, and the client was billed at cost plus 50%. All other jobs remained in process.

Required:
1.

Prepare a brief job-order cost sheet showing the October 1 balances of all four jobs, plus the direct materials and direct labor costs during October. There is no need to calculate applied overhead at this point or to total the costs.

2. Calculate the overhead applied to each job during October.
3. Calculate the balance in Work in Process on October 31.
4. What is the price of Job 877?

Homework Answers

Answer #1

1. Job-order cost sheet :

Job 877 Job 878 Job 879 Job 880
Opening WIP 18710 0 0 0
Direct Materials 14,380 5,960 3,550 1,790
Direct Labor 14,600 8,200 1,700 1,900
Total Costs 47690 14160 5250 3690

2. Calculation of Overhead applied to each job:

Job 877 = 14600*80% = 11680

Job 878 = 8200*80% = 6560

Job 879 = 1700*80% = 1360

Job 890 = 1900*80% = 1520

3. Work in Progress:

Job 878 Job 879 Job 880
Opening WIP 0 0 0
Direct Materials 5,960 3,550 1,790
Direct Labor 8,200 1,700 1,900
Overhead applied 6560 1360 1520
Total Costs 20,720 6,610 5,210

Total Work in Progress = 20720+6610+5210 = 32540

4.

Opening WIP 18710
Direct Materials 14,380
Direct Labor 14,600
Overhead Applied 11,680
Total Costs 59370
Add: 50% of Cost 29685
Price of Job 877 89055
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers....
Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,700 and Job 94 with a beginning balance of $7,200. Jagjit applies overhead at the rate of $6 per direct labor hour. Direct labor wages average $18 per hour. Data on August costs for all jobs are as follows: Job 93 Job 94 Job 95 Job 96 Direct...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Assigning Overhead To A Job Beta Corp. applies overhead to jobs on the basis of direct...
Assigning Overhead To A Job Beta Corp. applies overhead to jobs on the basis of direct labor costs. Job X which was started and completed during the current period shows charges of $10,000 for direct materials, $16,000 for direct labor, and $12,000 for overhead on its job cost sheet. Job Y which still was in process at year end shows charges of $5,000 for direct materials, and $8,000 for direct labor. Required: Should any overhead cost be applied to Job...
Alpha Company applies overhead costs to jobs on the basis of direct labor costs, Job A,...
Alpha Company applies overhead costs to jobs on the basis of direct labor costs, Job A, which was started and completed during the current period, shows charges of $10,000 for direct materials, $16,000 for direct labor, and $12,000 for overhead on its job cost sheet. Job B, which was still in process at year end, shows charges of $5,000 for direct materials and $8,000 for direct labor. Required: 1. (5 pts.) Should any overhead cost be applied to Job B...
Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V,...
Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $5,000 for direct materials, $9,700 for direct labor, and $6,596 for overhead on its job cost sheet. Job W, which is still in process at year-end, shows charges of $4,400 for direct materials and $4,400 for direct labor. Required: 1a. Should any overhead cost be applied to Job W at year-end? Yes...
A company which uses a job-costing system, had two jobs in process at the start of...
A company which uses a job-costing system, had two jobs in process at the start of February 2018: Job no. J6 with a cost of $110,000 and job no. F1 with a cost of $22,000. The following information is available: The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead and machine activity for the year were anticipated to be $3,366,000 and 102,000 hours, respectively. The company worked on four jobs during February. Direct materials used, direct...
ABC Manufacturing uses normal costing and allocates manufacturing overhead to jobs based on a budgeted direct...
ABC Manufacturing uses normal costing and allocates manufacturing overhead to jobs based on a budgeted direct labor-hour rate for the actual direct labor hours. Any overallocated or underallocated overhead is written-off to the cost of goods sold at the end of the month. During April 2019, ABC Manufacturing recorded the following: Budgeted manufacturing overhead costs: $400,000 Budgeted direct labor-hours: 20,000 DLHRS Budgeted machine hours: 16,000 MHRS Actual manufacturing overhead costs: $360,000 Actual direct labor-hours:   22,500 DLHRS Actual machine hours: 15,000...
Br3-Pf Company uses a job-order costing system and applies overhead costs to jobs using a plant-wide...
Br3-Pf Company uses a job-order costing system and applies overhead costs to jobs using a plant-wide rate of 90% of direct materials cost. Br3-Pf Company began work on four jobs during June. Information related to the four jobs appears below: Job #1 Job #2 COSTS ADDED DURING JUNE direct materials .............. $5,800 $7,500 direct labor .................. $7,300 $6,300 Job #3 Job #4 COSTS ADDED DURING JUNE direct materials .............. $8,200 $6,400 direct labor .................. $7,920 $7,560 By the end of...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. The company's predetermined overhead rate of $2.80 per machine-hour was based on a cost formula that estimates $232,400 of total manufacturing overhead for an estimated activity level of 83,000 machine-hours. Required: 1. Assume that during the year the company works only 78,000 machine-hours and incurs the following costs in the Manufacturing Overhead and Work in Process accounts: Compute the amount of overhead...