New Office Equipment List price: $37,200; terms: 2/10, n/30; paid within the discount period. Transportation-in: $870. Installation: $520. Cost to repair damage during unloading: $682. Routine maintenance cost after eight months: $240. Basket Purchase of Copier, Computer, and Scanner for $52,400 with Fair Market Values Copier, $26,502. Computer, $10,096. Scanner, $26,502. Land for New Warehouse with an Old Building Torn Down Purchase price, $83,300. Demolition of building, $5,350. Lumber sold from old building, $2,920. Grading in preparation for new building, $9,500. Construction of new building, $206,000. Required In each of these cases, determine the amount of cost to be capitalized in the asset accounts. Office equipment: Basket purchase: Land and building:
Amount of cost to be capitalized in the asset accounts are as calculated below:
Office Equipment | |
List Price | 37,200 |
Less: Discount (37,200*2%) | -744 |
Transportation In | 870 |
Installation | 520 |
Cost of Office equipment | 37,846 |
Basket Purchase | Fair Value | Percentage | Apportionment | ||
Copier | $26,502 | 26,502/63,100 | 0.42 | 52,400*0.42 | $22,008 |
Computer | $10,096 | 10,096/63,100 | 0.16 | 52,400*.16 | $8,384 |
Scanner | $26,502 | 26,502/63,100 | 0.42 | 52,400*0.42 | $22,008 |
Total | $63,100 | 1 | $52,400 |
Building
Amount ($) | |
Construction of new building | 206,000 |
Land for New Warehouse with an Old Building Torn Down Purchase price | 83,300 |
Demolition of building | 5,350 |
Lumber sold from old building | -2,920 |
Grading in preparation for new building | 9,500 |
Cost of Land and Building | 301,230 |