Glassworks Inc. produces two types of glass shelving, rounded
edge and squared edge, on the same production line. For the current
period, the company reports the following data.
|
Rounded Edge |
Squared Edge |
|
Total |
|
Direct materials |
|
$ |
9,500 |
|
|
$ |
21,700 |
|
$ |
31,200 |
|
Direct labor |
|
|
6,100 |
|
|
|
12,000 |
|
|
18,100 |
|
Overhead (300% of direct labor cost) |
|
|
18,300 |
|
|
|
36,000 |
|
|
54,300 |
|
Total cost |
|
$ |
33,900 |
|
|
$ |
69,700 |
|
$ |
103,600 |
|
Quantity produced |
|
|
10,300 |
ft. |
|
|
14,100 |
ft. |
|
|
|
Average cost per ft. (rounded) |
|
$ |
3.29 |
|
|
$ |
4.94 |
|
|
|
|
|
Glassworks's controller wishes to apply activity-based costing
(ABC) to allocate the $54,300 of overhead costs incurred by the two
product lines to see whether cost per foot would change markedly
from that reported above. She has collected the following
information.
Overhead Cost Category
(Activity Cost Pool) |
Cost |
Supervision |
|
$ |
2,172 |
|
Depreciation of machinery |
|
|
29,000 |
|
Assembly line preparation |
|
|
23,128 |
|
Total overhead |
|
$ |
54,300 |
|
|
She has also collected the following information about the cost
drivers for each category (cost pool) and the amount of each driver
used by the two product lines. (Round activity rate and
cost per unit answers to 2 decimal places.)
|
|
Usage |
Overhead Cost Category
(Activity Cost Pool) |
Driver |
Rounded Edge |
Squared Edge |
Total |
Supervision |
Direct labor cost ($) |
$ |
6,100 |
|
$ |
12,000 |
|
$ |
18,100 |
|
Depreciation of machinery |
Machine hours |
|
400 |
hours |
|
700 |
hours |
|
1,100 |
hours |
Assembly line preparation |
Setups (number) |
|
31 |
times |
|
94 |
times |
|
125 |
times |
|
|