Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow:
Direct Labor-Hours per Unit |
Annual Production | |
Hubs | 0.50 | 25,000 units |
Sprockets | 0.10 | 41,000 units |
Additional information about the company follows:
a. Hubs require $28 in direct materials per unit, and Sprockets require $12.
b. The direct labor wage rate is $19 per hour.
c. Hubs are more complex to manufacture than Sprockets and they require special processing.
d. The company’s activity-based absorption costing system has the following activity cost pools:
Estimated | Expected Activity | ||||
Activity Cost Pool (and Activity Measure) | Overhead Cost | Hubs | Sprockets | Total | |
Machine setups (number of setups) | $ | 14,850 | 75 | 60 | 135 |
Special processing (machine-hours) | $ | 148,000 | 3,700 | 0 | 3,700 |
General factory (Direct labor-hours) | $ | 116,200 | 12,500 | 4,100 | 16,600 |
Required:
1. Compute the activity rate for each activity cost pool.
2. Compute the unit product cost for Hubs and Sprockets using activity-based absorption costing.
Overhead cost | Expected Activity | Activity rate | |
Machine setups | 14850 | 135 | 110 |
Special processing | 148000 | 3700 | 40 |
General factory | 116200 | 16600 | 7 |
2 | |||
Hubs | Sockets | ||
Machine setups | 8250 | 6600 | |
Special processing | 148000 | 0 | |
General factory | 87500 | 116200 | |
Total | 243750 | 122800 | |
Units | 25000 | 41000 | |
Overhead per unit | 9.75 | 3.00 | |
Hubs | Sockets | ||
Direct materials | 28 | 12 | |
Direct labor | 9.5 | 1.9 | |
Overhead per unit | 9.75 | 3.00 | |
Unit product cost | 47.25 | 16.90 |