skynet (PDI) recently started operations to obtain a share of the growing flight market. PDI manufactures...

skynet (PDI) recently started operations to obtain a share of the growing flight market. PDI manufactures two models of specialty drivers: The X1 model and the X2 model. The company was formed as a partnership by two professional engineers and a professional piolet, none of whom had any accounting experience. The business has been very successful, and to cope with the increased level of activity, the partners have hired a professional accountant as their controller. One of the first improvements the controller wants is an update of the costing system, changing from a single overhead application rate using direct labour-hours to activity-based costing. The controller has identified the following three activities as cost drivers, along with the related cost pools:

Model

# of Materials Required

# of Product Inspections

# of Orders Shipped

X1

460

170

167

X2

620

240

129

Total Costs in Pool

$594,000

$82,000

$185,000

Required:

Using ABC, prepare a schedule that shows the allocation of the costs of each cost pool for each model. Show your calculations.

Homework Answers

Answer #1
Modex X1 Modex X2
No of materials Required 460 620
Cost per material $550 $550
Materials cost $253,000 $341,000
No of Product inspeciton 170 240
Cost per inpsection $200 $200
Product inspeciton $34,000 $48,000
No of Orders shipped 167 129
Cost per order $625 $625
Ordering cost $104,375 $80,625
Total cost allocated $391,375 $469,625

Working Notes:

Activity Cost pool Cost Drivers Drivers ABC Rate
Materials required $594,000 No of Materials required 1080 $550
Product inspeciton $82,000 No of Product inspeciton 410 $200
Orders $185,000 No of Orders shipped 296 $625
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions