MatchPoint Racket Company manufactures two types of tennis rackets, the Junior and Pro Striker models. The production budget for March for the two rackets is as follows:
Junior | Pro Striker | |
Production budget | 6,900 units | 21,800 units |
Both rackets are produced in two departments, Forming and Assembly. The direct labor hours required for each racket are estimated as follows:
Forming Department | Assembly Department | |
Junior | 0.2 hour per unit | 0.4 hour per unit |
Pro Striker | 0.3 hour per unit | 0.65 hour per unit |
The direct labor rate for each department is as follows:
Forming Department | $14 per hour |
Assembly Department | $9 per hour |
Prepare the direct labor cost budget for March.
MatchPoint Racket Company | ||
Direct Labor Cost Budget | ||
For the Month Ending March 31 | ||
Forming Department |
Assembly Department |
|
Hours required for production: | ||
Junior | ||
Pro Striker | ||
Total hours required | ||
Hourly rate | x$ | x$ |
Total direct labor cost | $ | $ |