16. Georgia, Inc. has collected the following data on one of its
products. The direct materials price variance is:
Direct materials standard (3 lbs @ $1/lb) | $3 | per finished unit |
Total direct materials cost variance—unfavorable | $26,250 | |
Actual direct materials used | 140,000 | lbs. |
Actual finished units produced | 35,000 | units |
Multiple Choice
$8,750 favorable.
$8,750 unfavorable.
$30,750 favorable.
$35,000 unfavorable.
Incorrect$26,250 unfavorable.
19, Georgia, Inc. has collected the following data on one of its
products. The direct materials quantity variance is:
Direct materials standard (3 lbs @ $1/lb) | $3 | per finished unit |
Total direct materials cost variance—unfavorable | $24,750 | |
Actual direct materials used | 120,000 | lbs. |
Actual finished units produced | 30,000 | units |
Multiple Choice
$24,750 unfavorable.
$30,000 favorable.
$30,000 unfavorable.
$5,250 favorable.
$24,750 favorable.
20. The following company information is available for March.
The direct materials price variance is:
Direct materials purchased and used | 3,600 feet @ $80 per foot | |
Standard costs for direct materials for March production | 3,700 feet @ $78 per foot | |
Multiple Choice
$7,200 unfavorable.
$7,200 favorable.
$7,400 unfavorable.
$7,400 favorable.
$600 favorable.
21. Fletcher Company collected the following data regarding
production of one of its products. Compute the total
direct labor cost variance.
Direct labor standard (2 hrs. @ $12.75/hr.) | $ | 25.50 | per finished unit | |
Actual direct labor hours | 62,500 | hrs. | ||
Actual finished units produced | 31,000 | units | ||
Actual cost of direct labor | $ | 870,300 | ||
Multiple Choice
$6,375 favorable.
$73,425 unfavorable.
$73,425 favorable.
$79,800 favorable.
$79,800 unfavorable.
Answer 16 |
Standard cost for material- Actual cost = DM cost varinace |
( 35000 * 3 ) - ( 140000 * AP ) = - 26250 |
105000 - 140000 AP = - 26250 |
140000 AP = 131250 |
AP = $ 0.9375 |
DMPV = ( SP - AP ) * AQ purchased |
( 1 - 0.9375) * 140000 = $ 8750 ( fav. ) |
Option A is correct. |
Answer 19 |
DMQV = ( SQ allowed - AQ ) * SP |
[ ( 30000 * 3 ) - 120000 ] * 1 |
$ 30000 ( unfav. ) |
Option C is correct. |
Answer 20 |
DMPV = ( SP - AP ) * AQ purchased |
( 78 - 80 ) * 3600 = $ 7200 ( Unfav. ) |
Option A is correct. |
Answer 21 |
DLCV = Standard cost for labour- Actual cost |
( 31000 * 25.5 ) - 870300 |
$ 79800 ( unfav. ) |
Option E is correct. |
Get Answers For Free
Most questions answered within 1 hours.